5560 N ELMER AVE 91601

Certificate Information: 5560 N ELMER AVE 91601

Application / Permit
24010-20000-01398
Plan Check / Job No.
B24VN04567
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***eplan***: New detached Two Story ADU PER LAMC 12.22 A.33(c) AND (d) at rear of property.
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 YASHAR EMAMI
Corrections Issued 4/17/2024 YASHAR EMAMI
Re-Submittal Required 4/30/2024 CHIHARU SUZUKI
Re-Submitted 5/3/2024 YASHAR EMAMI
Corrections Issued 2 5/3/2024 YASHAR EMAMI
Submitted for Second Quality Review 5/3/2024 YASHAR EMAMI
Quality Review Completed 5/7/2024 CHIHARU SUZUKI
Applicant returned to address corrections 2/19/2025 YASHAR EMAMI
Applicant returned to address corrections 3/5/2025 YASHAR EMAMI
Applicant returned to address corrections 3/19/2025 YASHAR EMAMI
Applicant returned to address corrections 4/10/2025 YASHAR EMAMI
Plan Check Approved 4/15/2025 YASHAR EMAMI
Issued 4/16/2025 APPLICANT
CofO in Progress 4/22/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 5/28/2026 RUBEN SALAS
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/18/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/19/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/19/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 9/19/2024 SARAH YOUSSEF
Frnt yard landscape/Water mgmt Cleared 11/14/2024 DALIA MOKAYED
Roof/Waste drainage to street Cleared 11/15/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/22/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 4/29/2025 Not Ready for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 5/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 7/28/2025 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 7/28/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/29/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/31/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 7/31/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 8/14/2025 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 8/14/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 8/26/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/26/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/26/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/26/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 10/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 10/29/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/12/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 2/27/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/27/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/20/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/20/2026 Approved ROBERTO PALACIOS-LOPEZ