127-127 1/2 W 59TH PL 90003
Certificate Information: 127-127 1/2 W 59TH PL 90003
- Application / Permit
- 24010-20000-01385
- Plan Check / Job No.
- B24VN04526
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *EPLAN* NEW 92'-6" X 25' DUPLEX WITH 3-CAR GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | SELLA BENYAMIN |
| Corrections Issued | 4/16/2024 | SELLA BENYAMIN |
| Quality Review Completed | 4/19/2024 | STEVEN KIM |
| Applicant returned to address corrections | 9/24/2024 | SELLA BENYAMIN |
| Plan Check Approved | 10/8/2024 | SELLA BENYAMIN |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 3/5/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
| CofO Issued | 3/12/2025 | DEROLD HAUFF |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/23/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 5/15/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 5/22/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 5/24/2024 | TREVOR QUAN |
| Highway dedication | Cleared | 5/29/2024 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 7/5/2024 | GILBERT URREA |
| Permit | Cleared | 7/16/2024 | TREVOR QUAN |
| Trees in Parkway | Cleared | 9/10/2024 | ADALBERTO VERA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/6/2024 | Approved | AMIR NAZARIAN |
| Special/Order Compliance | 11/6/2024 | Partial Inspection | ALEX COLIN |
| BUILDING-Rough-Frame | 11/18/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 11/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 12/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/27/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 1/7/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/7/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 2/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/18/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/4/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/4/2025 | Approved | ALEJANDRO DE ARTOLA |