6563 N BLEWETT AVE 91406

Certificate Information: 6563 N BLEWETT AVE 91406

Application / Permit
24010-20000-01378
Plan Check / Job No.
B24VN04513
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 51'-0" X 25'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/3/2025
Issuing Office
Valley
Current Status
CofO in Progress on 6/23/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2024 APPLICANT
Assigned to Plan Check Engineer 4/10/2024 ARTIN ZARUKIAN
Corrections Issued 4/15/2024 ARTIN ZARUKIAN
Building Plans Picked Up 4/16/2024 APPLICANT
Plan Check Approved 8/19/2025 ANGELICA MARTINEZ
Issued 9/3/2025 APPLICANT
CofO in Progress 6/23/2026 MATTHEW NELSON

Permit Application Clearance Information

Address approval Cleared 4/16/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/16/2024 CARLOS AGUILERA
ZI Cleared 6/24/2024 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 1/21/2025 CARLOS AGUILERA
Sewer availability Cleared 1/21/2025 CARLOS AGUILERA
Construction near power lines Cleared 1/22/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/20/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/23/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 10/23/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/17/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/17/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/17/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 11/17/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 11/17/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 11/17/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/21/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 11/21/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 11/21/2025 Approved GAREN HAYRAPETYAN
Insulation 12/17/2025 Partial Approval CHRISTOPHER MORFIN
Interior/Exterior Lathing 12/17/2025 Partial Approval CHRISTOPHER MORFIN
Drywall Nailing 12/22/2025 Not Ready for Inspection MICHAEL CORTEZ
Green Building Rough 12/22/2025 Not Ready for Inspection MICHAEL CORTEZ
BUILDING-Rough-Frame 12/24/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 12/24/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/24/2025 Approved GAREN HAYRAPETYAN
Shower Pan 12/24/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 5/5/2026 Approved KIRK SANDERS
Drywall Nailing 6/15/2026 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 6/17/2026 Approved MICHAEL CORTEZ
Final 6/17/2026 Corrections Issued MICHAEL CORTEZ
HVAC-Final 6/17/2026 Approved MICHAEL CORTEZ
Drywall Nailing 6/22/2026 Approved MATTHEW NELSON
Final 6/22/2026 OK to Issue CofO MATTHEW NELSON
Green Building Final 6/22/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/22/2026 SGSOV Approved MATTHEW NELSON
Service/Power Release 6/22/2026 Approved MATTHEW NELSON
Smoke Detectors 6/22/2026 Approved MATTHEW NELSON