9639 N COLUMBUS AVE 91343
Certificate Information: 9639 N COLUMBUS AVE 91343
- Application / Permit
- 24010-20000-01371
- Plan Check / Job No.
- B24VN04465
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- EplanL New 1-Story Detached ALQ. Per engineering design.
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | DAVID CASTILLO |
| Corrections Issued | 4/9/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/18/2024 | DAVID CASTILLO |
| Plan Check Approved | 6/26/2024 | ALFREDO JARA |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 2/7/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
| CofO Issued | 2/13/2025 | RUBEN SALAS |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/24/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/29/2024 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 6/15/2024 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/5/2024 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/24/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 11/15/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/18/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/18/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 11/18/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 12/5/2024 | Conditional Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 12/12/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/12/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/4/2025 | Approved | JENNIFER RABUCHIN |
| Final | 2/4/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/4/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/4/2025 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 2/4/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/7/2025 | Approved | JENNIFER RABUCHIN |
| Final | 2/7/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 2/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/7/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/7/2025 | Approved | JENNIFER RABUCHIN |