3151 3/4 S CURTS AVE 90034

Certificate Information: 3151 3/4 S CURTS AVE 90034

Application / Permit
24010-20000-01365
Plan Check / Job No.
B24VN04423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one story irregular shaped 25' 9" x 34' ADU per CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g), all work done per engineer.
Permit Issued
Issued on 9/5/2024
Issuing Office
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 NAREG ATARIAN
Corrections Issued 4/7/2024 NAREG ATARIAN
Quality Review Completed 4/8/2024 OMID HEDAYAT
Building Plans Picked Up 4/9/2024 APPLICANT
Plan Check Approved 8/30/2024 NAREG ATARIAN
Issued 9/5/2024 APPLICANT
CofO in Progress 6/27/2025 EVAN COOPER
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 4/19/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 4/19/2024 DAVID LOPEZ
ZI Cleared 4/19/2024 ALEX VELA
Address approval Cleared 4/24/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/24/2024 DAVID LOPEZ
Sewer availability Cleared 4/24/2024 DAVID LOPEZ
Community Plan Implem. Overlay Cleared 4/30/2024 COLLINS ALLAN
Specific Plan Cleared 4/30/2024 COLLINS ALLAN
Community Plan Implem. Overlay Cleared 8/13/2024 ISAIAH ROSS
ZI Cleared 8/13/2024 ISAIAH ROSS
Construction near power lines Cleared 8/15/2024 RIDWAN HARDY
Construction within easement Cleared 8/15/2024 RIDWAN HARDY
Specific Plan Cleared 8/27/2024 JULISSA LOPEZ-HODOYAN
ZI Cleared 8/27/2024 JULISSA LOPEZ-HODOYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/29/2024 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/30/2024 Approved ARAM AVEDISIAN
Deputy Wood Construction 11/20/2024 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Approved MEL KHACHATOURIAN
HVAC-Rough 12/2/2024 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 12/2/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 1/6/2025 Approved BOBBY KEY
HVAC-Rough 1/6/2025 Approved BOBBY KEY
PLUMBING-Rough 1/6/2025 Corrections Issued BOBBY KEY
Special/Order Compliance 1/6/2025 Partial Inspection JAYLIN GRAVITTE
BUILDING-Rough-Frame 1/10/2025 Approved MEL KHACHATOURIAN
Green Building Rough 1/10/2025 Approved MEL KHACHATOURIAN
MERV13>=Rough 1/10/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 1/10/2025 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 1/10/2025 Approved MEL KHACHATOURIAN
Insulation 1/14/2025 Approved ARAM AVEDISIAN
Drywall Nailing 1/27/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 1/27/2025 Approved MEL KHACHATOURIAN
Shower Pan 1/27/2025 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 5/16/2025 Corrections Issued EVAN COOPER
Service/Power Release 5/16/2025 Approved EVAN COOPER
HVAC-Final 5/23/2025 Approved EVAN COOPER
PLUMBING-Final 5/23/2025 Approved EVAN COOPER
ELECTRICAL-Final 6/27/2025 Approved EVAN COOPER
Final 6/27/2025 OK to Issue CofO EVAN COOPER
Green Building Final 6/27/2025 Approved EVAN COOPER
MERV13>=Final 6/27/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 6/27/2025 Approved EVAN COOPER