6419 N WHITE OAK AVE 91335
Certificate Information: 6419 N WHITE OAK AVE 91335
- Application / Permit
- 24010-20000-01355
- Plan Check / Job No.
- B24VN04389
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE WITH ADDITION INTO A 2-STORY (42'-10" X 27' IRREGULAR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) - (d) WITH AN ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 4/18/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 4/18/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/24/2024 | APPLICANT |
| Applicant returned to address corrections | 4/30/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 7/29/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 8/16/2024 | VAHAN JIVALAGIAN |
| Issued | 8/16/2024 | APPLICANT |
| CofO in Progress | 1/7/2025 | ARUTYUN MADATYAN |
| CofO Issued | 3/27/2025 | JOHN JANSON |
| Permit Finaled | 3/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 5/24/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 5/24/2024 | TAL SHEMEN |
| ZI | Cleared | 6/17/2024 | ASHLEY RODARTE |
| Construction near power lines | Cleared | 7/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/27/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/13/2024 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 9/13/2024 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 9/17/2024 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 9/18/2024 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 10/3/2024 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | JEFFREY BULL |
| Sewer | 10/3/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 10/3/2024 | Partial Approval | JEFFREY BULL |
| Deputy Wood Construction | 10/23/2024 | Conditional Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Corrections Issued | JEFFREY BULL |
| PLUMBING-Rough | 10/28/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/1/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 11/1/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 11/1/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 11/1/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 11/1/2024 | Partial Approval | JEFFREY BULL |
| Insulation | 11/8/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Underground Mechanical | 11/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 11/25/2024 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 12/3/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/20/2024 | Corrections Issued | JEFFREY HARTLINE |
| Final | 12/20/2024 | Corrections Issued | JEFFREY HARTLINE |
| Gas Test | 12/20/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 12/20/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/20/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 12/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 12/20/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 1/6/2025 | Approved | ARUTYUN MADATYAN |
| Final | 1/6/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 1/6/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/6/2025 | Approved | ARUTYUN MADATYAN |