503 1/4-1/2 E 64TH ST 90003
Certificate Information: 503 1/4-1/2 E 64TH ST 90003
- Application / Permit
- 24010-20000-01348
- Plan Check / Job No.
- B24VN04362
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW 2-STORY ADUs (2UNITS) PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- Issued on 7/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | KHEDER ALRAZAA |
| Corrections Issued | 4/18/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 4/23/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/8/2024 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 6/5/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 7/16/2024 | KHEDER ALRAZAA |
| Issued | 7/16/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2024 | CELINA MORENO |
| Sewer availability | Cleared | 5/8/2024 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 5/25/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 6/12/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/10/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 1/29/2025 | Approved | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 2/12/2025 | Conditional Approval | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 2/26/2025 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 3/28/2025 | Conditional Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Corrections Issued | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Rough | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/12/2025 | Partial Approval | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Wood Frame | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Rough | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| Verify Sprinkler Sign Off | 5/19/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| BUILDING-Rough-Frame | 6/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 6/6/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 6/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 6/6/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 6/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 6/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 6/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 6/13/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| Wood Frame | 6/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 6/17/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/17/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 6/20/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 6/25/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/25/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/2/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/16/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/18/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/31/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/8/2025 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Insulation | 8/22/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/22/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 9/16/2025 | Corrections Issued | ANTHONY RAMOS |
| Green Building Rough | 9/16/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 9/25/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/19/2025 | Approved | ANTHONY RAMOS |
| Sewer | 6/3/2026 | No Access for Inspection | ALEX COLIN |
| Sewer | 6/5/2026 | No Result Entered | JOHN QUINTANILLA |