5061 N BELLINGHAM AVE 91607
Certificate Information: 5061 N BELLINGHAM AVE 91607
- Application / Permit
- 24010-20000-01325
- Plan Check / Job No.
- B23VN18060
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) PER ENGINEERING
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- Issued on 11/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | ALFRED RAMIREZ |
| Corrections Issued | 4/6/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/10/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 6/5/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 10/10/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/29/2024 | MOHAMMAD ESMAILI |
| Issued | 11/5/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/9/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 4/24/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 4/24/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 4/24/2024 | DANIEL CORONADO |
| Specific Plan | Cleared | 4/29/2024 | CHRISTIAN PEARSON |
| ZI | Cleared | 4/29/2024 | CHRISTIAN PEARSON |
| Construction near power lines | Cleared | 10/8/2024 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 10/8/2024 | ENRIQUE ACOSTA |
Contact Information
| Contractor | United Construction Group Inc; Lic. No.: 1077065-B | 1731 W 55TH ST LOS ANGELES, CA 90062 |
| Engineer | Ramos,, Victor; Lic. No.: C86568 | 4823 ALMAGUER AVE GUADALUPE, CA 93434 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 11/22/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/2/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 12/2/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/11/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 12/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 12/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/13/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 12/31/2024 | Partial Approval | KEVIN BERBERYAN |
| Underground Mechanical | 12/31/2024 | Approved | KEVIN BERBERYAN |
| Sewer | 1/16/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Rough | 1/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Rough-Elec/Plmb/HVAC | 1/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 1/31/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 2/21/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 2/24/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 2/24/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 2/24/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/28/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 2/28/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 3/5/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/5/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/13/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/17/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/6/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 7/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |