13151 N CRANSTON AVE 91342
Certificate Information: 13151 N CRANSTON AVE 91342
- Application / Permit
- 24010-20000-01323
- Plan Check / Job No.
- B24VN04301
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN (N) DETACHED 874 SF ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | ALFREDO JARA |
| Corrections Issued | 4/6/2024 | ALFREDO JARA |
| Plan Check Approved | 7/8/2024 | ALFREDO JARA |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 1/27/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
| CofO Issued | 2/13/2025 | RUBEN SALAS |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/26/2024 | CHARLES POWELL |
| Address approval | Cleared | 4/30/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/30/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/9/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/1/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2024 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 7/8/2024 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/24/2024 | Partial Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 10/31/2024 | Approved | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 11/4/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/5/2024 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/25/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/25/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 11/25/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/25/2024 | Conditional Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/25/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/2/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 12/2/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 12/6/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/10/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 12/26/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 1/13/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 1/21/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Final | 1/21/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| Final | 1/24/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/31/2025 | Approved | KEVIN BERBERYAN |