10321 N TELFAIR AVE 91331
Certificate Information: 10321 N TELFAIR AVE 91331
- Application / Permit
- 24010-20000-01303
- Plan Check / Job No.
- B24VN04251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 24'-0" X 40'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER WFPP ***COMPLY WITH DEPARTMENT ORDER effective date 12/18/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 10/3/2024
- Issuing Office
- Current Status
- Issued on 10/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 4/8/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 8/14/2024 | OMAR GARNICA |
| Plan Check Approved | 10/1/2024 | OMAR GARNICA |
| Issued | 10/3/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 4/16/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 5/21/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/30/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/7/2024 | Approved | RAUL VASQUEZ |
| Pre-Inspection | 11/7/2024 | Approved | RAUL VASQUEZ |
| Underground Mechanical | 11/7/2024 | Approved | RAUL VASQUEZ |
| Deputy Reinf. Concrete | 11/12/2024 | Approved | RAUL VASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Not Ready for Inspection | RAUL VASQUEZ |
| PLUMBING-Rough | 11/21/2024 | Partial Approval | RAUL VASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2025 | Approved | RAUL VASQUEZ |
| Green Building Rough | 1/3/2025 | Approved | RAUL VASQUEZ |
| Underground Mechanical | 1/3/2025 | Approved | RAUL VASQUEZ |
| Interior/Exterior Lathing | 2/6/2025 | Approved | RAUL VASQUEZ |
| ELECTRICAL-Rough | 3/4/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| HVAC-Rough | 3/4/2025 | Approved | RAUL VASQUEZ |
| PLUMBING-Rough | 3/4/2025 | Approved | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | RAUL VASQUEZ |
| Drywall Nailing | 4/15/2025 | Approved | RAUL VASQUEZ |
| ELECTRICAL-Rough | 4/15/2025 | Approved | RAUL VASQUEZ |
| METHANE-Rough | 4/15/2025 | Approved | RAUL VASQUEZ |
| Verify Sprinkler Sign Off | 4/15/2025 | Approved | RAUL VASQUEZ |
| Service/Power Release | 4/25/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Service/Power Release | 6/10/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Final | 8/8/2025 | Conditional Approval | MARK VAN SLOOTEN |
| Footing/Foundation/Slab | 8/8/2025 | Approved | MARK VAN SLOOTEN |
| Green Building Final | 8/8/2025 | Approved | MARK VAN SLOOTEN |
| METHANE-Barrier | 8/8/2025 | Approved | MARK VAN SLOOTEN |
| METHANE-Subgrade | 8/8/2025 | Approved | MARK VAN SLOOTEN |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | MARK VAN SLOOTEN |
| Service/Power Release | 8/8/2025 | Approved | MARK VAN SLOOTEN |
| Smoke Detectors | 8/8/2025 | Approved | MARK VAN SLOOTEN |