130 1/4-1/2 W 59TH PL 90003
Certificate Information: 130 1/4-1/2 W 59TH PL 90003
- Application / Permit
- 24010-20000-01215
- Plan Check / Job No.
- B24VN03925
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY 2-UNIT ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | DANIEL YIP |
| Corrections Issued | 3/30/2024 | DANIEL YIP |
| Quality Review Completed | 4/2/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/29/2024 | DANIEL YIP |
| Plan Check Approved | 6/11/2024 | DANIEL YIP |
| Issued | 6/24/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | JOSE MACIAS |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/9/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 5/9/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 5/14/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | 21226 VENTURA BLVD 250 WOODLAND HILLS, CA 91364 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | MICHAEL LEWIS |
| Deputy Wood Construction | 8/30/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/10/2024 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 9/10/2024 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 9/10/2024 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 9/10/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 10/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 10/15/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/17/2024 | Approved | JOSH MEISTER |
| Shower Pan | 10/17/2024 | Approved | JOSH MEISTER |
| Sewer | 11/4/2024 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 11/4/2024 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 1/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/25/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 2/25/2025 | Approved | JOSE MACIAS |