19146 W KESWICK ST 91335

Certificate Information: 19146 W KESWICK ST 91335

Application / Permit
24010-20000-01183
Plan Check / Job No.
B24VN03804
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 45'-11" X 17'-0" IRREGULARLY SHAPED, DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT (702.50 SF) PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. BUILDING SHALL BE FULLY FIRE SPRINKLERED THROUGH OUT WITH NFPA 13D
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
CofO Issued on 4/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2024 APPLICANT
Assigned to Plan Check Engineer 3/29/2024 KAMYAR EMAMI
Corrections Issued 4/1/2024 KAMYAR EMAMI
Applicant returned to address corrections 4/12/2024 MADISON ODELL
Applicant returned to address corrections 4/16/2024 PINANK PATEL
Applicant returned to address corrections 4/23/2024 PINANK PATEL
Applicant returned to address corrections 5/11/2024 PINANK PATEL
Plan Check Approved 6/7/2024 KAMYAR EMAMI
Issued 6/11/2024 APPLICANT
CofO in Progress 3/19/2025 ARUTYUN MADATYAN
Permit Finaled 4/11/2025 JOHN JANSON
CofO Issued 4/11/2025 JOHN JANSON
Permit Finaled 4/11/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/8/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/8/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/8/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 4/29/2024 WALTER RAMIREZ
Low Impact Development (LID) Cleared 5/17/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 5/29/2024 BIAINA HARITUNIAN

Contact Information

Contractor Susan Development And Construction Inc; Lic. No.: 1089492-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/28/2024 Corrections Issued SEAN WIRCH
Underground Mechanical 7/9/2024 Partial Approval JEFFREY BULL
Footing/Foundation/Slab 7/16/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 8/29/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Partial Approval JEFFREY HARTLINE
HVAC-Rough 8/29/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 9/9/2024 Approved JEFFREY BULL
Green Building Rough 9/9/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 9/9/2024 Partial Approval JEFFREY BULL
PLUMBING-Rough 9/9/2024 Approved JEFFREY BULL
Shower Pan 9/9/2024 Approved JEFFREY BULL
Verify Sprinkler Sign Off 9/9/2024 Approved JEFFREY BULL
Insulation 9/11/2024 Not Ready for Inspection SCOTT SOBEL
Interior/Exterior Lathing 9/11/2024 Approved SCOTT SOBEL
Insulation 9/13/2024 Approved JEFFREY BULL
Drywall Nailing 9/19/2024 Approved JEFFREY BULL
ELECTRICAL-Final 2/24/2025 Approved ARUTYUN MADATYAN
Final 2/24/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 2/24/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 2/24/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 2/24/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 2/24/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 2/24/2025 Approved ARUTYUN MADATYAN
Final 3/18/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 3/18/2025 Approved ARUTYUN MADATYAN
Service/Power Release 3/18/2025 Approved ARUTYUN MADATYAN