5708-5710 N DENNY AVE 91601
Certificate Information: 5708-5710 N DENNY AVE 91601
- Application / Permit
- 24010-20000-01180
- Plan Check / Job No.
- B24VN03795
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: REMOVE EXISTING GARAGE ATTACHED TO SINGLE FAMILY DWELLING AND ADD (29'-5" X 15') 1- CAR GARAGE WITH COVERED PATIO AND SECOND STORY ACCESSORY DWELLING UNIT ABOVE PER LAMC 12.22 A.33 (c) AND (e)
- Permit Issued
- Issued on 11/14/2024
- Issuing Office
- Current Status
- Issued on 11/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 4/6/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 4/8/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/16/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 10/11/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 10/21/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 11/13/2024 | VAHAN JIVALAGIAN |
| Issued | 11/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 5/9/2024 | DALIA MOKAYED |
| Miscellaneous | Cleared | 5/9/2024 | DALIA MOKAYED |
| Roof/Waste drainage to street | Cleared | 10/22/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/7/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/25/2025 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 3/28/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/28/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Approved | JOSE AVILA |
| Deputy Reinf. Concrete | 4/7/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Corrections Issued | JOSE AVILA |
| Wood Frame | 5/16/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 6/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 6/25/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/20/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/20/2025 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 9/3/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 9/3/2025 | Approved | JOSE AVILA |
| Deputy Wood Construction | 9/8/2025 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 9/11/2025 | Approved | JOSE AVILA |
| Green Building Rough | 9/11/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 9/11/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/29/2025 | Partial Approval | JOSE AVILA |
| Insulation | 10/10/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 10/28/2025 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 11/3/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/5/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 5/6/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Special/Order Compliance | 5/7/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 5/19/2026 | Approved | GAREN HAYRAPETYAN |