12730 1/2 N BROMONT AVE 91340
Certificate Information: 12730 1/2 N BROMONT AVE 91340
- Application / Permit
- 24010-20000-01172
- Plan Check / Job No.
- B24VN03741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 26'-6" X 26 TWO STORY DWELLING PER SB9 TO EXISTING DETACHED GARAGE
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | SELLA BENYAMIN |
| Corrections Issued | 4/2/2024 | SELLA BENYAMIN |
| Quality Review Completed | 4/3/2024 | STEVEN KIM |
| Plan Check Approved | 2/4/2025 | SELLA BENYAMIN |
| Issued | 2/4/2025 | APPLICANT |
| Building Plans Picked Up | 9/29/2025 | APPLICANT |
| CofO in Progress | 10/20/2025 | KEVIN BERBERYAN |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 11/19/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/2/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 1/22/2025 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/23/2025 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/24/2025 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2025 | Partial Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 2/20/2025 | Approved | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 2/24/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 3/20/2025 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 3/20/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 3/26/2025 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/8/2025 | No Access for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 4/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/23/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 4/23/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 4/23/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 4/23/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/23/2025 | Approved | KEVIN BERBERYAN |
| MERV13>=Rough | 4/23/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/23/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/29/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 4/29/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 5/9/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 5/13/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/19/2025 | Approved | LOUIS ESCOTO |
| HVAC-Rough | 5/19/2025 | Approved | LOUIS ESCOTO |
| Final | 9/22/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/22/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 9/22/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Final | 9/22/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Smoke Detectors | 9/22/2025 | Approved | KEVIN BERBERYAN |
| Final | 10/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 10/3/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 10/3/2025 | Not Required | KEVIN BERBERYAN |
| Final | 10/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| Final | 10/10/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 10/10/2025 | Not Required | KEVIN BERBERYAN |