7463 N SUNNY BRAE AVE 91306
Certificate Information: 7463 N SUNNY BRAE AVE 91306
- Application / Permit
- 24010-20000-01168
- Plan Check / Job No.
- B24VN03720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED PATIO COVER & TRELLIS (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 12/31/2024
- Issuing Office
- Current Status
- Issued on 12/31/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/7/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/12/2024 | JASON HEALEY |
| Applicant returned to address corrections | 7/8/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/18/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/12/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/9/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/26/2024 | NILOOFAR MEHRAIN |
| Issued | 12/31/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/17/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 5/10/2024 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 5/20/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/25/2024 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 8/27/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/27/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/22/2025 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 1/29/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/29/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Deputy Wood Construction | 4/4/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 5/16/2025 | Approved | ALEXANDER HANDY |
| Sewer | 5/16/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 5/16/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 5/28/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 5/28/2025 | Approved | ALEXANDER HANDY |
| Insulation | 6/3/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/3/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Drywall Nailing | 6/9/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 7/8/2025 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 6/23/2026 | No Access for Inspection | TROY SANDERS |