14555 W LYLE ST 91342
Certificate Information: 14555 W LYLE ST 91342
- Application / Permit
- 24010-20000-01118
- Plan Check / Job No.
- B24VN03204
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN New one story 35' x 40' ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineer.
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | NAREG ATARIAN |
| Corrections Issued | 3/17/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/22/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/16/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 5/23/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/1/2024 | NAREG ATARIAN |
| Plan Check Approved | 8/16/2024 | NAREG ATARIAN |
| Issued | 9/4/2024 | APPLICANT |
| CofO in Progress | 3/12/2025 | KEVIN BERBERYAN |
| CofO in Progress | 7/2/2025 | JOAQUIN GREENOUGH |
| CofO in Progress | 8/15/2025 | KEVIN BERBERYAN |
| CofO Issued | 8/15/2025 | RUBEN SALAS |
| Permit Finaled | 8/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/26/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 8/2/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/9/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/19/2024 | Conditional Approval | KEVIN BERBERYAN |
| Structural Steel Frame | 9/19/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/11/2024 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 10/11/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/17/2024 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 10/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 10/23/2024 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 10/23/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/25/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/25/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | KEVIN BERBERYAN |
| Final | 2/27/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 2/27/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 2/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Service/Power Release | 2/27/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 2/27/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/6/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 3/6/2025 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 7/2/2025 | Corrections Issued | KEVIN BERBERYAN |
| Final | 8/15/2025 | OK to Issue CofO | KEVIN BERBERYAN |