10028 N STONEHURST PL 91040
Certificate Information: 10028 N STONEHURST PL 91040
- Application / Permit
- 24010-20000-01111
- Plan Check / Job No.
- B24VN03552
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-6" X 30'-10" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Valley
- Current Status
- Issued on 5/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | SELLA BENYAMIN |
| Corrections Issued | 4/4/2024 | SELLA BENYAMIN |
| Quality Review Completed | 4/5/2024 | STEVEN KIM |
| Building Plans Picked Up | 4/8/2024 | APPLICANT |
| Plan Check Approved | 5/7/2024 | SELLA BENYAMIN |
| Issued | 5/7/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/13/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/13/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/13/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Street Frontage | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/18/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/17/2025 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 1/28/2025 | Corrections Issued | DAVID ANDERSON |
| Sewer | 3/6/2025 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 3/19/2025 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 4/11/2025 | Partial Approval | DAVID ANDERSON |
| Deputy Reinf. Concrete | 4/23/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/28/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 6/9/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/9/2025 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Approved | DAVID ANDERSON |
| Pre-Inspection | 8/20/2025 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 9/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 9/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 9/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Special/Order Compliance | 9/15/2025 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 9/15/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/2/2025 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/2/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 10/2/2025 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 10/2/2025 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/2/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 10/2/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/17/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/17/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 10/17/2025 | Approved | DAVID ANDERSON |
| Insulation | 10/21/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/21/2025 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 10/21/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 10/28/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/10/2026 | Approved | DAVID ANDERSON |