7705 1/2 N TAMPA AVE 91335

Certificate Information: 7705 1/2 N TAMPA AVE 91335

Application / Permit
24010-20000-01086
Plan Check / Job No.
B24VN03501
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached two story 27' x 24' ADU per LAMC 12.22 A.33 (c)-(d) with attached Porch. NFPA 13D sprinkler required. All work done per engineer.
Permit Issued
Issued on 11/8/2024
Issuing Office
Current Status
CofO Issued on 2/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 NAREG ATARIAN
Corrections Issued 3/24/2024 NAREG ATARIAN
Quality Review Completed 3/27/2024 OMID HEDAYAT
Building Plans Picked Up 3/28/2024 APPLICANT
Applicant returned to address corrections 8/14/2024 NAREG ATARIAN
Plan Check Approved 11/8/2024 NAREG ATARIAN
Issued 11/8/2024 APPLICANT
CofO in Progress 2/5/2026 ARUTYUN MADATYAN
Permit Finaled 2/6/2026 JOHN JANSON
CofO Issued 2/6/2026 JOHN JANSON
Permit Finaled 2/6/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/15/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 7/10/2024 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 7/17/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/17/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 8/6/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/7/2025 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 3/20/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Wood Construction 5/13/2025 Conditional Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 9/9/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Approved ARUTYUN MADATYAN
Green Building Rough 9/9/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 9/9/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 9/9/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/9/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 9/9/2025 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 9/15/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/22/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 10/22/2025 Approved ARUTYUN MADATYAN
Insulation 11/5/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 11/7/2025 Approved ARUTYUN MADATYAN
Final 1/20/2026 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 1/20/2026 Approved ARUTYUN MADATYAN
Green Building Final 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 1/20/2026 Approved ARUTYUN MADATYAN
Final 1/26/2026 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 1/26/2026 Approved ARUTYUN MADATYAN
Service/Power Release 1/26/2026 Approved ARUTYUN MADATYAN