14115 W WEIDNER ST 91331
Certificate Information: 14115 W WEIDNER ST 91331
- Application / Permit
- 24010-20000-01061
- Plan Check / Job No.
- B24VN03409
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-2" X 20'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 3/19/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/20/2024 | APPLICANT |
| Plan Check Approved | 9/11/2024 | YAQUB MIRZA |
| Issued | 9/11/2024 | APPLICANT |
| CofO in Progress | 7/30/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 3/22/2024 | ROGELIO CORTES |
| Sewer availability | Cleared | 3/22/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 3/27/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 8/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 2/27/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 2/27/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 2/27/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 3/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Final | 3/24/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 4/2/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/2/2025 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/2/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/9/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/9/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/11/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/11/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 4/21/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/25/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/25/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 5/21/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/18/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Not Required | JENNIFER RABUCHIN |
| Service/Power Release | 7/18/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/24/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/24/2025 | Approved | JENNIFER RABUCHIN |