11158 N HASKELL AVE 91344
Certificate Information: 11158 N HASKELL AVE 91344
- Application / Permit
- 24010-20000-01018
- Plan Check / Job No.
- B24VN03221
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New Detached 2 Story ADU . per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/18/2025
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | GARO TELMI |
| Corrections Issued | 3/30/2024 | GARO TELMI |
| Quality Review Completed | 4/17/2024 | CHAD DOI |
| Applicant returned to address corrections | 11/7/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/15/2024 | GARO TELMI |
| Plan Check Approved | 12/3/2024 | GARO TELMI |
| Issued | 3/18/2025 | APPLICANT |
| No Progress | 9/29/2025 | RAUL OLAGI |
| CofO in Progress | 9/29/2025 | RAUL OLAGI |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/7/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/8/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 10/12/2024 | CHARLES POWELL |
| Construction near power lines | Cleared | 10/24/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 10/24/2024 | TINA MIRANDA |
| Low Impact Development (LID) | Cleared | 11/11/2024 | JORGE MEJIA LEMUS |
| GPI Written Notices | Cleared | 11/13/2024 | GERMAN RODRIGUEZ MENDOZA |
| Roof/Waste drainage to street | Cleared | 11/14/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Delmar Construction Inc; Lic. No.: 1117613-B | , |
| Engineer | Matevosyan,, Nzhde; Lic. No.: C92008 | 10853 NASSAU AVE SUNLAND, CA 91040 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 4/4/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Grounding or Bonding | 4/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 4/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/14/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 5/14/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/23/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/3/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/6/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/6/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 6/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 6/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 6/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 6/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/10/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/10/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/10/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 8/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 8/6/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 9/17/2025 | Approved | JENNIFER RABUCHIN |
| Final | 9/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 9/17/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/17/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/17/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/17/2025 | Approved | JENNIFER RABUCHIN |