13616 W PIERCE ST 91331
Certificate Information: 13616 W PIERCE ST 91331
- Application / Permit
- 24010-20000-01013
- Plan Check / Job No.
- B24VN03210
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New one story 34' 6" x 36' ADU per LAMC 12.22 A.33 (c)-(d), with attached patio cover. All work done per engineer.
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- Issued on 12/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | NAREG ATARIAN |
| Corrections Issued | 4/4/2024 | NAREG ATARIAN |
| Quality Review Completed | 4/9/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/1/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/18/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 11/21/2024 | NAREG ATARIAN |
| Plan Check Approved | 12/26/2024 | NAREG ATARIAN |
| Issued | 12/27/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/14/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 12/10/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/10/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Sewer | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/30/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/30/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 1/30/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/30/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/11/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/11/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/21/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/5/2025 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/5/2025 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Rough | 12/5/2025 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 12/5/2025 | No Access for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 12/5/2025 | No Access for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 12/5/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/5/2025 | No Access for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/5/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/8/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 12/8/2025 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 12/8/2025 | Approved | MICHEL ABAJAN |
| Insulation | 12/11/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/22/2025 | Approved | MICHEL ABAJAN |