6626 N TAMPA AVE 91335

Certificate Information: 6626 N TAMPA AVE 91335

Application / Permit
24010-20000-00985
Plan Check / Job No.
B24VN03134
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Dettached Garage Conversion at Rear of the lot to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/4/2024
Issuing Office
Current Status
CofO Issued on 11/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 EDWIN ESPIN
Corrections Issued 3/18/2024 EDWIN ESPIN
Plan Check Approved 4/3/2024 EDWIN ESPIN
Issued 4/4/2024 APPLICANT
CofO in Progress 10/23/2024 JEFFREY BULL
Permit Finaled 11/27/2024 JOHN JANSON
CofO Issued 11/27/2024 JOHN JANSON
Permit Finaled 11/27/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/19/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/19/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/21/2024 CARLOS RAMIREZ
ZI Cleared 3/27/2024 STEVEN WECHSLER

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: NA22676       ,
Contractor Mega Development & Construction Inc; Lic. No.: 1102277-B       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/29/2024 Approved JEFFREY BULL
Deputy Drilled-In Anchors 5/7/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 5/7/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 7/2/2024 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 7/2/2024 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 7/2/2024 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 7/24/2024 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 7/24/2024 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 7/24/2024 Not Ready for Inspection ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Approved JEFFREY BULL
HVAC-Rough 7/29/2024 Approved JEFFREY BULL
PLUMBING-Rough 7/29/2024 Approved JEFFREY BULL
Smoke Detectors 7/29/2024 Partial Approval JEFFREY BULL
HVAC-Rough 8/2/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 8/2/2024 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 8/6/2024 Partial Approval TROY SANDERS
Insulation 8/9/2024 Approved JEFFREY BULL
Drywall Nailing 8/21/2024 Approved JEFFREY BULL
ELECTRICAL-Final 9/13/2024 Not Ready for Inspection JEFFREY BULL
Final 9/13/2024 Corrections Issued JEFFREY BULL
Green Building Final 9/13/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Final 9/13/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 9/13/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 9/13/2024 Approved JEFFREY BULL
Final 10/2/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 10/2/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV Approved JEFFREY BULL
Final 10/15/2024 Corrections Issued JEFFREY BULL
Green Building Final 10/15/2024 Approved JEFFREY BULL
Final 10/23/2024 OK to Issue CofO JEFFREY BULL