2010 E 95TH ST 90002
Certificate Information: 2010 E 95TH ST 90002
- Application / Permit
- 24010-20000-00958
- Plan Check / Job No.
- B24VN03085
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 34'-9" X 35'-7" DETACHED ACCESSORY DWELLING UNIT WITH OPEN TRELLIS PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 3/18/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/18/2024 | APPLICANT |
| Plan Check Approved | 6/14/2024 | JESSE ARELLANO |
| Issued | 6/18/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | ANTHONY EGSON |
| Permit Finaled | 9/17/2025 | ANSON MAGLASANG |
| CofO Issued | 9/17/2025 | ANSON MAGLASANG |
| Permit Finaled | 9/17/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 5/2/2024 | JESSICA OPINION |
| Low Impact Development (LID) | Cleared | 6/10/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/12/2024 | TREVOR QUAN |
Contact Information
| Contractor | 129 Builders Inc; Lic. No.: 1051295-B | 1223 WILSHIRE BLVD #931 SANTA MONICA, CA 90403 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 7/6/2024 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 7/6/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/6/2024 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 7/29/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 7/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 8/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Corrections Issued | BEN MOLSTAD |
| Deputy Wood Construction | 8/5/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | BEN MOLSTAD |
| Insulation | 8/5/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 8/8/2024 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 8/19/2024 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 8/19/2024 | No Access for Inspection | BEN MOLSTAD |
| Green Building Rough | 8/19/2024 | No Access for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 8/19/2024 | No Access for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 8/19/2024 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/26/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/26/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 11/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 11/26/2024 | Corrections Issued | ANTHONY EGSON |
| Deputy Wood Construction | 11/27/2024 | Conditional Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/6/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/6/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 12/6/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 12/6/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/6/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 12/10/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 12/11/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Off-Hour Fees Due | |
| Green Building Rough | 12/13/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/13/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 12/24/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/24/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/6/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/25/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 4/25/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 4/29/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 4/29/2025 | Approved | ANTHONY EGSON |
| Final | 6/2/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/2/2025 | Approved | ANTHONY EGSON |
| Green Building Final | 6/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 6/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 6/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 7/1/2025 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 7/1/2025 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/1/2025 | Approved | JOHN KLARIN |
| Final | 7/15/2025 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/15/2025 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 7/15/2025 | Not Ready for Inspection | JOHN KLARIN |
| Final | 8/15/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 8/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 8/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 8/29/2025 | Approved | ANTHONY EGSON |
| Final | 8/29/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 8/29/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 8/29/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 8/29/2025 | Approved | ANTHONY EGSON |
| Service/Power Release | 8/29/2025 | Approved | ANTHONY EGSON |