2010 E 95TH ST 90002

Certificate Information: 2010 E 95TH ST 90002

Application / Permit
24010-20000-00958
Plan Check / Job No.
B24VN03085
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 34'-9" X 35'-7" DETACHED ACCESSORY DWELLING UNIT WITH OPEN TRELLIS PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 6/18/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2024 APPLICANT
Assigned to Plan Check Engineer 3/13/2024 ARTIN ZARUKIAN
Corrections Issued 3/18/2024 ARTIN ZARUKIAN
Building Plans Picked Up 3/18/2024 APPLICANT
Plan Check Approved 6/14/2024 JESSE ARELLANO
Issued 6/18/2024 APPLICANT
CofO in Progress 8/29/2025 ANTHONY EGSON
Permit Finaled 9/17/2025 ANSON MAGLASANG
CofO Issued 9/17/2025 ANSON MAGLASANG
Permit Finaled 9/17/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/30/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 5/2/2024 JESSICA OPINION
Sewer availability Cleared 5/2/2024 JESSICA OPINION
Low Impact Development (LID) Cleared 6/10/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/12/2024 TREVOR QUAN

Contact Information

Contractor 129 Builders Inc; Lic. No.: 1051295-B 1223 WILSHIRE BLVD #931      SANTA MONICA, CA 90403
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2024 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 7/6/2024 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 7/6/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 7/6/2024 Off-Hour Fees Due
BUILDING-Rough-Frame 7/29/2024 Partial Approval BEN MOLSTAD
Green Building Rough 7/29/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 7/29/2024 Not Ready for Inspection BEN MOLSTAD
Insulation 8/1/2024 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Corrections Issued BEN MOLSTAD
Deputy Wood Construction 8/5/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval BEN MOLSTAD
Insulation 8/5/2024 Partial Approval BEN MOLSTAD
Footing/Foundation/Slab 8/8/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 8/19/2024 No Access for Inspection BEN MOLSTAD
ELECTRICAL-Rough 8/19/2024 No Access for Inspection BEN MOLSTAD
Green Building Rough 8/19/2024 No Access for Inspection BEN MOLSTAD
PLUMBING-Rough 8/19/2024 No Access for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 8/19/2024 No Access for Inspection BEN MOLSTAD
ELECTRICAL-Rough 10/29/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Not Ready for Inspection ANTHONY EGSON
Wood Frame 10/29/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/26/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 11/26/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 11/26/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 11/26/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 11/26/2024 Corrections Issued ANTHONY EGSON
Deputy Wood Construction 11/27/2024 Conditional Approval ANTHONY EGSON
BUILDING-Rough-Frame 12/6/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/6/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 12/6/2024 Approved ANTHONY EGSON
HVAC-Rough 12/6/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 12/6/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/10/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 12/11/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/13/2024 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Off-Hour Fees Due
Green Building Rough 12/13/2024 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/13/2024 Approved JOSEPH MCGARRY
Insulation 12/24/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/24/2024 Approved ANTHONY EGSON
Drywall Nailing 1/6/2025 Approved ANTHONY EGSON
PLUMBING-Rough 4/25/2025 Corrections Issued ANTHONY EGSON
Sewer 4/25/2025 Corrections Issued ANTHONY EGSON
Sewer 4/29/2025 Approved ANTHONY EGSON
Underground Mechanical 4/29/2025 Approved ANTHONY EGSON
Final 6/2/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 6/2/2025 Approved ANTHONY EGSON
Green Building Final 6/2/2025 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Not Required ANTHONY EGSON
Service/Power Release 6/2/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 6/2/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Final 7/1/2025 Corrections Issued JOHN KLARIN
Service/Power Release 7/1/2025 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 7/1/2025 Approved JOHN KLARIN
Final 7/15/2025 Corrections Issued JOHN KLARIN
Green Building Final 7/15/2025 Corrections Issued JOHN KLARIN
Service/Power Release 7/15/2025 Not Ready for Inspection JOHN KLARIN
Final 8/15/2025 Corrections Issued ANTHONY EGSON
Green Building Final 8/15/2025 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 8/15/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 8/29/2025 Approved ANTHONY EGSON
Final 8/29/2025 OK to Issue CofO ANTHONY EGSON
Green Building Final 8/29/2025 Approved ANTHONY EGSON
HVAC-Final 8/29/2025 Approved ANTHONY EGSON
PLUMBING-Final 8/29/2025 Approved ANTHONY EGSON
Service/Power Release 8/29/2025 Approved ANTHONY EGSON