17511 W STARE ST 91325

Certificate Information: 17511 W STARE ST 91325

Application / Permit
24010-20000-00955
Plan Check / Job No.
B24VN03066
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (N) 2-STORY ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/16/2024
Issuing Office
Current Status
CofO Issued on 3/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 KHEDER ALRAZAA
Corrections Issued 3/18/2024 KHEDER ALRAZAA
Quality Review Completed 4/4/2024 GARO TELMI
Applicant returned to address corrections 5/29/2024 KHEDER ALRAZAA
Applicant returned to address corrections 6/24/2024 KHEDER ALRAZAA
Plan Check Approved 10/11/2024 KHEDER ALRAZAA
Issued 10/16/2024 APPLICANT
CofO in Progress 2/20/2026 CHRISTOPHER ROJAS
CofO Issued 3/17/2026 RUBEN SALAS
Permit Finaled 3/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/10/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/10/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 5/17/2024 GILBERT URREA
Construction near power lines Cleared 5/30/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 9/23/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 9/23/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/21/2024 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 10/30/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 10/30/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/1/2024 No Access for Inspection JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 11/18/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/18/2024 Approved MISAEL ESPARZA
Deputy Other (see comments) 1/16/2025 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 1/17/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 2/3/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 2/3/2025 Approved JAVIER RAMOS JR
Pre-Inspection 2/11/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/26/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 2/26/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/17/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 3/17/2025 Corrections Issued JAVIER RAMOS JR
Shower Pan 3/17/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/1/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/1/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/1/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/7/2025 Partial Approval NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/7/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/7/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/15/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 4/15/2025 Approved NICHOLAS TROWBRIDGE
Insulation 5/5/2025 Approved KEVIN BERBERYAN
Drywall Nailing 5/23/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 5/23/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/23/2025 Approved CHRISTOPHER ROJAS
Sewer 7/17/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Final 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Final 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Final 10/2/2025 Approved NICHOLAS TROWBRIDGE
Service/Power Release 10/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/9/2025 Approved NICHOLAS TROWBRIDGE
Final 10/9/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/9/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Not Required NICHOLAS TROWBRIDGE
Service/Power Release 10/9/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 10/9/2025 Approved NICHOLAS TROWBRIDGE
Final 1/6/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 1/6/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 1/6/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 1/21/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/21/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 1/21/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 1/26/2026 Corrections Issued JOSE AVILA
Service/Power Release 1/26/2026 Corrections Issued JOSE AVILA
ELECTRICAL-Final 2/12/2026 Approved JENNIFER RABUCHIN
Final 2/12/2026 Partial Approval JENNIFER RABUCHIN
HVAC-Final 2/12/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/12/2026 Approved JENNIFER RABUCHIN
Service/Power Release 2/12/2026 Approved JENNIFER RABUCHIN
Final 2/20/2026 OK to Issue CofO CHRISTOPHER ROJAS