1323 E 46TH ST 90011
Certificate Information: 1323 E 46TH ST 90011
- Application / Permit
- 24010-20000-00931
- Plan Check / Job No.
- B24VN02966
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW 26'-0" x 20'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 4/8/2024
- Issuing Office
- Current Status
- Issued on 4/8/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 3/9/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 3/14/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 4/4/2024 | GIOVANNY CHAVEZ |
| Issued | 4/8/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 3/13/2024 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 3/28/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 4/2/2024 | TREVOR QUAN |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Underground Mechanical | 5/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/21/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 5/21/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/31/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Wood Construction | 8/5/2025 | Conditional Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 8/8/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 8/8/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 8/13/2025 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 8/13/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 8/13/2025 | Corrections Issued | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 8/13/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 8/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/26/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 8/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 8/26/2025 | Corrections Issued | LUIS CASTRO |
| Verify Sprinkler Sign Off | 8/26/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/3/2025 | Not Ready for Inspection | LUIS CASTRO |
| Interior/Exterior Lathing | 10/3/2025 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/9/2025 | No Access for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 11/6/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 11/6/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 11/6/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 11/6/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 11/18/2025 | Corrections Issued | ALEX COLIN |
| Insulation | 11/18/2025 | Conditional Approval | ALEX COLIN |
| Drywall Nailing | 12/5/2025 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/5/2025 | Approved | ANTHONY RAMOS |