12761 N EL DORADO AVE 91342

Certificate Information: 12761 N EL DORADO AVE 91342

Application / Permit
24010-20000-00928
Plan Check / Job No.
B24VN02948
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (N) DETACHED ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/24/2024
Issuing Office
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 JOHNPAUL ISIP
Corrections Issued 3/12/2024 JOHNPAUL ISIP
Plan Check Approved 9/2/2024 ALFREDO JARA
Issued 9/24/2024 APPLICANT
CofO in Progress 11/18/2025 KEVIN BERBERYAN
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/10/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/10/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 8/26/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/28/2024 BIAINA HARITUNIAN
GPI Written Notices Cleared 9/2/2024 JOHNPAUL ISIP
Grading Pre-Inspection Cleared 9/2/2024 JOHNPAUL ISIP

Contact Information

Architect Kivotos,, Juan M; Lic. No.: NA26491       ,
Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: NA43720       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2024 Partial Inspection KEVIN BERBERYAN
Underground Mechanical 11/4/2024 Approved KEVIN BERBERYAN
Underground Mechanical 11/12/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 11/26/2024 Corrections Issued KEVIN BERBERYAN
Reinforced Concrete Frame 11/26/2024 Not Ready for Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 12/4/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 12/24/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 2/4/2025 Partial Approval KEVIN BERBERYAN
Green Building Rough 2/4/2025 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 3/3/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/3/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 3/18/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 3/24/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 3/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 3/24/2025 Conditional Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 3/27/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 3/27/2025 Approved KEVIN BERBERYAN
Insulation 3/27/2025 Conditional Approval KEVIN BERBERYAN
PLUMBING-Rough 3/27/2025 Approved KEVIN BERBERYAN
Drywall Nailing 4/15/2025 Approved KEVIN BERBERYAN
Green Building Rough 4/15/2025 Approved KEVIN BERBERYAN
Shower Pan 5/8/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 5/29/2025 Approved KEVIN BERBERYAN
Final 9/9/2025 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV No Gas KEVIN BERBERYAN
Smoke Detectors 9/9/2025 Approved KEVIN BERBERYAN
Final 10/30/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 10/30/2025 Approved KEVIN BERBERYAN
Service/Power Release 10/30/2025 Approved KEVIN BERBERYAN
Final 11/18/2025 OK to Issue CofO KEVIN BERBERYAN