7660 N LEMP AVE 91605
Certificate Information: 7660 N LEMP AVE 91605
- Application / Permit
- 24010-20000-00899
- Plan Check / Job No.
- B24VN02838
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 7/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 3/9/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/11/2024 | APPLICANT |
| Applicant returned to address corrections | 3/20/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/20/2024 | ROSENDO MEDINA |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 7/19/2024 | MATTHEW NELSON |
| Permit Finaled | 7/26/2024 | RUBEN SALAS |
| CofO Issued | 7/26/2024 | RUBEN SALAS |
| Permit Finaled | 7/26/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/12/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 3/19/2024 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 3/19/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 3/20/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/29/2024 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Approved | MATTHEW NELSON |
| Sewer | 4/15/2024 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 4/15/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/26/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 4/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/26/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 4/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/7/2024 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 5/7/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/8/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/8/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/8/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/8/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/13/2024 | Corrections Issued | LEONARD ROSS II |
| Interior/Exterior Lathing | 5/15/2024 | Approved | MATTHEW NELSON |
| Insulation | 5/20/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 5/20/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/21/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 5/21/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/23/2024 | Approved | MATTHEW NELSON |
| Final | 7/10/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/10/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 7/10/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 7/10/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 7/10/2024 | Approved | MATTHEW NELSON |
| Final | 7/18/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 7/18/2024 | Approved | MATTHEW NELSON |
| Service/Power Release | 7/18/2024 | Approved | MATTHEW NELSON |