7309 N FARMDALE AVE 91605
Certificate Information: 7309 N FARMDALE AVE 91605
- Application / Permit
- 24010-20000-00896
- Plan Check / Job No.
- B24VN02833
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 1-story Accessory Dwelling Unit (42' x 37'-6" Irregular Shape) per LAMC 12.22 A.33 (c) - (d). NFPA 13D Fire Sprinklers Throughout. All work per Wood Frame Prescriptive Provisions except engineering provided for a beam and california roof framing.
- Permit Issued
- Issued on 5/5/2024
- Issuing Office
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 3/23/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 3/28/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/1/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 5/2/2024 | VAHAN JIVALAGIAN |
| Issued | 5/5/2024 | APPLICANT |
| CofO in Progress | 3/13/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
| CofO Issued | 4/17/2025 | RUBEN SALAS |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/9/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 4/12/2024 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 4/24/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 4/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 7/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/5/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/5/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 8/5/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/28/2024 | Approved | JOSE AVILA |
| Green Building Rough | 8/28/2024 | Approved | JOSE AVILA |
| Shower Pan | 8/28/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 8/28/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/29/2024 | Corrections Issued | JOSE AVILA |
| Insulation | 9/5/2024 | Conditional Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | MICHAEL CORTEZ |
| Shower Pan | 9/5/2024 | Partial Inspection | MICHAEL CORTEZ |
| Drywall Nailing | 9/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/23/2024 | Approved | GAREN HAYRAPETYAN |
| Sewer | 11/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 11/7/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Final | 12/3/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 12/3/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 12/3/2024 | No Access for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 12/3/2024 | Approved | JACK KARGODORIAN |
| Final | 2/27/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/27/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 3/13/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 3/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |