7309 N FARMDALE AVE 91605

Certificate Information: 7309 N FARMDALE AVE 91605

Application / Permit
24010-20000-00896
Plan Check / Job No.
B24VN02833
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 1-story Accessory Dwelling Unit (42' x 37'-6" Irregular Shape) per LAMC 12.22 A.33 (c) - (d). NFPA 13D Fire Sprinklers Throughout. All work per Wood Frame Prescriptive Provisions except engineering provided for a beam and california roof framing.
Permit Issued
Issued on 5/5/2024
Issuing Office
Current Status
CofO Issued on 4/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 VAHAN JIVALAGIAN
Corrections Issued 3/23/2024 VAHAN JIVALAGIAN
Quality Review Completed 3/28/2024 OMID HEDAYAT
Applicant returned to address corrections 5/1/2024 VAHAN JIVALAGIAN
Plan Check Approved 5/2/2024 VAHAN JIVALAGIAN
Issued 5/5/2024 APPLICANT
CofO in Progress 3/13/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/17/2025 RUBEN SALAS
CofO Issued 4/17/2025 RUBEN SALAS
Permit Finaled 4/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/8/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/9/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/9/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 4/12/2024 WALTER RAMIREZ
Low Impact Development (LID) Cleared 4/24/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/26/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/12/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 6/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Approved JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 7/23/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/5/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Approved VINCENT HANLEY
HVAC-Rough 8/5/2024 Approved VINCENT HANLEY
PLUMBING-Rough 8/5/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/28/2024 Approved JOSE AVILA
Green Building Rough 8/28/2024 Approved JOSE AVILA
Shower Pan 8/28/2024 Approved JOSE AVILA
Verify Sprinkler Sign Off 8/28/2024 Approved JOSE AVILA
Interior/Exterior Lathing 8/29/2024 Corrections Issued JOSE AVILA
Insulation 9/5/2024 Conditional Approval MICHAEL CORTEZ
Interior/Exterior Lathing 9/5/2024 Partial Approval MICHAEL CORTEZ
Shower Pan 9/5/2024 Partial Inspection MICHAEL CORTEZ
Drywall Nailing 9/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/23/2024 Approved GAREN HAYRAPETYAN
Sewer 11/7/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 11/7/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Final 12/3/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 12/3/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Approved JACK KARGODORIAN
Service/Power Release 12/3/2024 No Access for Inspection JACK KARGODORIAN
Smoke Detectors 12/3/2024 Approved JACK KARGODORIAN
Final 2/27/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/27/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 3/13/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/13/2025 Approved ROBERTO PALACIOS-LOPEZ