22913 W SHERMAN WAY 91307
Certificate Information: 22913 W SHERMAN WAY 91307
- Application / Permit
- 24010-20000-00851
- Plan Check / Job No.
- B24VN02746
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story Accessory Dwelling Unit (29' x 23'-6") per LAMC 12.22 A.33 (c) - (d)
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 3/19/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 3/20/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/5/2024 | APPLICANT |
| Applicant returned to address corrections | 9/9/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 9/23/2024 | VAHAN JIVALAGIAN |
| Issued | 11/7/2024 | APPLICANT |
| CofO in Progress | 3/12/2026 | JEFFREY HARTLINE |
| Permit Finaled | 4/7/2026 | JOHN JANSON |
| CofO Issued | 4/7/2026 | JOHN JANSON |
| Permit Finaled | 4/7/2026 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 8/20/2024 | LUIS LUVANO |
| Address approval | Cleared | 8/22/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/22/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/22/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/23/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Alsa Build And Design Group; Lic. No.: 1110459-B | 1875 KELTON AVE #202 LOS ANGELES, CA 90025 |
| Engineer | Isaac,, Raymond; Lic. No.: C84605 | 19546 ROSITA ST TARZANA, CA 91356 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/6/2024 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 12/6/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 12/27/2024 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/31/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 1/31/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/11/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 3/11/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 4/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 4/25/2025 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 4/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 4/30/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 4/30/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 4/30/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 4/30/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 5/9/2025 | Approved | JEFFREY HARTLINE |
| Shower Pan | 5/9/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 6/5/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/5/2025 | Partial Approval | JEFFREY HARTLINE |
| Sewer | 7/31/2025 | Approved | JEFFREY HARTLINE |
| Final | 10/17/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 10/17/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Required | JEFFREY HARTLINE |
| Service/Power Release | 10/17/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 10/17/2025 | Approved | JEFFREY HARTLINE |
| Final | 3/6/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 3/6/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Service/Power Release | 3/6/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 3/13/2026 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 3/13/2026 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 3/13/2026 | Approved | JEFFREY HARTLINE |