22913 W SHERMAN WAY 91307

Certificate Information: 22913 W SHERMAN WAY 91307

Application / Permit
24010-20000-00851
Plan Check / Job No.
B24VN02746
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story Accessory Dwelling Unit (29' x 23'-6") per LAMC 12.22 A.33 (c) - (d)
Permit Issued
Issued on 11/7/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 VAHAN JIVALAGIAN
Corrections Issued 3/19/2024 VAHAN JIVALAGIAN
Quality Review Completed 3/20/2024 OMID HEDAYAT
Building Plans Picked Up 4/5/2024 APPLICANT
Applicant returned to address corrections 9/9/2024 VAHAN JIVALAGIAN
Plan Check Approved 9/23/2024 VAHAN JIVALAGIAN
Issued 11/7/2024 APPLICANT
CofO in Progress 3/12/2026 JEFFREY HARTLINE
Permit Finaled 4/7/2026 JOHN JANSON
CofO Issued 4/7/2026 JOHN JANSON
Permit Finaled 4/7/2026 JOHN JANSON

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/20/2024 LUIS LUVANO
Address approval Cleared 8/22/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/22/2024 LEE GUILBEAUX
Sewer availability Cleared 8/22/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/22/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/23/2024 LEE GUILBEAUX

Contact Information

Contractor Alsa Build And Design Group; Lic. No.: 1110459-B 1875 KELTON AVE   #202    LOS ANGELES, CA 90025
Engineer Isaac,, Raymond; Lic. No.: C84605 19546 ROSITA ST      TARZANA, CA 91356

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/6/2024 Approved JEFFREY HARTLINE
Underground Mechanical 12/6/2024 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 12/27/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/31/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 1/31/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 3/11/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 3/11/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 4/25/2025 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 4/25/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 4/25/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 4/30/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 4/30/2025 Approved JEFFREY HARTLINE
Green Building Rough 4/30/2025 Approved JEFFREY HARTLINE
HVAC-Rough 4/30/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 4/30/2025 Approved JEFFREY HARTLINE
Insulation 5/9/2025 Approved JEFFREY HARTLINE
Shower Pan 5/9/2025 Approved JEFFREY HARTLINE
Drywall Nailing 6/5/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/5/2025 Partial Approval JEFFREY HARTLINE
Sewer 7/31/2025 Approved JEFFREY HARTLINE
Final 10/17/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 10/17/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Required JEFFREY HARTLINE
Service/Power Release 10/17/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 10/17/2025 Approved JEFFREY HARTLINE
Final 3/6/2026 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 3/6/2026 Not Ready for Inspection JEFFREY HARTLINE
Service/Power Release 3/6/2026 Not Ready for Inspection JEFFREY HARTLINE
Final 3/13/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 3/13/2026 Approved JEFFREY HARTLINE
Service/Power Release 3/13/2026 Approved JEFFREY HARTLINE