6923 N FIRMAMENT AVE 91406

Certificate Information: 6923 N FIRMAMENT AVE 91406

Application / Permit
24010-20000-00834
Plan Check / Job No.
B24VN02697
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 64' X 33' ONE STORY DWELLING UNIT PER SB9; EQUIPPED WITH NFPA 13-R FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/16/2024
Issuing Office
Current Status
CofO Issued on 2/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 SELLA BENYAMIN
Corrections Issued 3/21/2024 SELLA BENYAMIN
Quality Review Completed 3/22/2024 STEVEN KIM
Building Plans Picked Up 3/28/2024 APPLICANT
Plan Check Approved 7/12/2024 SELLA BENYAMIN
Issued 7/16/2024 APPLICANT
CofO in Progress 2/11/2025 RYAN SALAZAR
Permit Finaled 2/19/2025 RUBEN SALAS
CofO Issued 2/19/2025 RUBEN SALAS
Permit Finaled 2/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/8/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/8/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/8/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 6/17/2024 LUIS LUVANO
Hydrant and Access approval Cleared 6/20/2024 KURT CORRAL
Roof/Waste drainage to street Cleared 6/20/2024 BIAINA HARITUNIAN
Senate Bill 9 Cleared 6/21/2024 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/31/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 8/5/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 8/5/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval RYAN SALAZAR
HVAC-Rough 8/30/2024 Approved RYAN SALAZAR
PLUMBING-Rough 8/30/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 9/18/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 9/18/2024 Approved VINCENT HANLEY
Green Building Rough 9/18/2024 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 9/18/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 9/18/2024 Approved VINCENT HANLEY
Deputy Wood Construction 9/19/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 9/23/2024 Approved RYAN SALAZAR
Green Building Rough 9/23/2024 Approved RYAN SALAZAR
Insulation 9/23/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/23/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 10/2/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/2/2024 Not Ready for Inspection RYAN SALAZAR
Shower Pan 10/2/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/16/2024 Approved RYAN SALAZAR
Sewer 11/1/2024 Approved RYAN SALAZAR
Underground Mechanical 11/8/2024 Approved RYAN SALAZAR
Final 12/16/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 12/16/2024 Approved RYAN SALAZAR
Green Building Final 12/16/2024 Approved RYAN SALAZAR
MERV13>=Final 12/16/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Required RYAN SALAZAR
Service/Power Release 12/16/2024 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 12/16/2024 Approved RYAN SALAZAR
Final 1/22/2025 Partial Approval RYAN SALAZAR
Service/Power Release 1/22/2025 Approved RYAN SALAZAR
Final 2/11/2025 OK to Issue CofO RYAN SALAZAR