4427 N ATOLL AVE 91423
Certificate Information: 4427 N ATOLL AVE 91423
- Application / Permit
- 24010-20000-00810
- Plan Check / Job No.
- B24VN02626
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE 19'X25' ONE STORY ACCESSORY DWELLING UNIT (PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g))_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 1/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | DAWN MC NULTY |
| Corrections Issued | 3/6/2024 | DAWN MC NULTY |
| Quality Review Completed | 3/7/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 3/20/2024 | APPLICANT |
| Applicant returned to address corrections | 5/22/2024 | DAWN MC NULTY |
| Plan Check Approved | 6/3/2024 | DAWN MC NULTY |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 10/24/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 1/22/2026 | RUBEN SALAS |
| CofO Issued | 1/22/2026 | RUBEN SALAS |
| Permit Finaled | 1/22/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/7/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 4/5/2024 | ROGELIO CORTES |
| ZI | Cleared | 4/22/2024 | DAVID URITA |
| Roof/Waste drainage to street | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 5/20/2024 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/18/2024 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/28/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/27/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 9/27/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 9/27/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 9/27/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 11/5/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 11/5/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/8/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 11/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/21/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/11/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 12/11/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/19/2024 | Approved | MISAEL ESPARZA |
| Final | 10/3/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 10/24/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Not Required | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 10/24/2025 | Approved | CHRISTOPHE COCHRAN |