6545 1/2 N VARNA AVE 91401

Certificate Information: 6545 1/2 N VARNA AVE 91401

Application / Permit
24010-20000-00785
Plan Check / Job No.
B24VN02566
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 34' X 19'ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/16/2024
Issuing Office
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 SELLA BENYAMIN
Corrections Issued 3/5/2024 SELLA BENYAMIN
Quality Review Completed 3/6/2024 STEVEN KIM
Building Plans Picked Up 3/8/2024 APPLICANT
Plan Check Approved 7/16/2024 SELLA BENYAMIN
Issued 7/16/2024 APPLICANT
CofO in Progress 12/24/2024 OGANES TARAKHCHYAN
CofO in Progress 12/26/2024 RAUL OLAGI
CofO in Progress 1/9/2025 RAUL OLAGI
Permit Finaled 1/15/2025 RUBEN SALAS
CofO Issued 1/15/2025 RUBEN SALAS
Permit Finaled 1/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/15/2024 CARLOS AGUILERA
Sewer availability Cleared 4/15/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 6/17/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 6/26/2024 CARLOS AGUILERA
Construction near power lines Cleared 7/2/2024 TINA MIRANDA

Contact Information

Contractor Productive Home Renovation Inc; Lic. No.: 1076623-B 12444 VICTORY BLVD #402      NORTH HOLLYWOOD, CA 91606
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2024 Approved OGANES TARAKHCHYAN
Special/Order Compliance 7/18/2024 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval OGANES TARAKHCHYAN
Insulation 7/22/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/16/2024 Corrections Issued ROBERT GOLD
Green Building Rough 8/16/2024 Approved ROBERT GOLD
Rough-Elec/Plmb/HVAC 8/16/2024 Corrections Issued ROBERT GOLD
Verify Sprinkler Sign Off 8/16/2024 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 8/22/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/22/2024 Corrections Issued SALVADOR MARTINEZ
Verify Sprinkler Sign Off 8/22/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/28/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 8/28/2024 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/30/2024 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/30/2024 Partial Approval OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 8/30/2024 Approved OGANES TARAKHCHYAN
Insulation 9/4/2024 Approved RYAN SALAZAR
Shower Pan 9/4/2024 Approved RYAN SALAZAR
Drywall Nailing 9/6/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/1/2024 Corrections Issued OGANES TARAKHCHYAN
Final 11/1/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 11/1/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 11/1/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/23/2024 Approved OGANES TARAKHCHYAN
Final 12/23/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Required OGANES TARAKHCHYAN
Service/Power Release 12/23/2024 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 12/23/2024 Approved OGANES TARAKHCHYAN