5939 N CARPENTER AVE 91607
Certificate Information: 5939 N CARPENTER AVE 91607
- Application / Permit
- 24010-20000-00775
- Plan Check / Job No.
- B24VN02496
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. New irregular shaped 28' 3" x 43' 1" single family dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21, NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 9/25/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | NAREG ATARIAN |
| Corrections Issued | 3/3/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/5/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/10/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/12/2024 | NAREG ATARIAN |
| Plan Check Approved | 9/19/2024 | NAREG ATARIAN |
| Issued | 9/25/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | JOSE AVILA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/1/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 6/11/2024 | JOHN CONNEALLY |
| Senate Bill 9 | Cleared | 6/17/2024 | ALEX VELA |
| Miscellaneous | Cleared | 7/3/2024 | GREGORIO GUILLERMO |
| Construction near power lines | Cleared | 7/9/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/9/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 9/3/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Platinum Home Builders & Design Inc; Lic. No.: 1072304-B | 5170 SEPULVEDA BLVD #280 SHERMAN OAKS, CA 91403 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/1/2024 | No Access for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/5/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 11/5/2024 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 11/13/2024 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 12/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/4/2024 | OK to Expire Permit | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 12/4/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/6/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/6/2024 | Partial Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 12/24/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/30/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 1/7/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/7/2025 | Approved | JOSE AVILA |
| Shower Pan | 1/7/2025 | Approved | JOSE AVILA |
| Underground Mechanical | 1/7/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/14/2025 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 1/14/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/17/2025 | Conditional Approval | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 1/17/2025 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 1/17/2025 | Approved | JOSE AVILA |
| Insulation | 1/23/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 2/5/2025 | Approved | JOSE AVILA |
| Sewer | 2/5/2025 | Approved | JOSE AVILA |
| Non Compliance | 2/26/2025 | Not Required | JOSE AVILA |
| Notice of Violation | 2/26/2025 | Not Required | JOSE AVILA |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/2/2025 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 5/2/2025 | Approved | JOSE AVILA |
| Final | 5/22/2025 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 5/22/2025 | Approved | JOSE AVILA |
| Final | 6/11/2025 | OK to Issue CofO | JOSE AVILA |