13269 W MONTAGUE ST 91331
Certificate Information: 13269 W MONTAGUE ST 91331
- Application / Permit
- 24010-20000-00758
- Plan Check / Job No.
- B24VN02447
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: SB 9 TWO UNIT DEVELOPMENTS NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE IN THE REAR OF THE LOT
- Permit Issued
- Issued on 2/13/2025
- Issuing Office
- Current Status
- Issued on 2/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | KHEDER ALRAZAA |
| Corrections Issued | 3/27/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 4/10/2024 | GARO TELMI |
| Plan Check Approved | 6/26/2024 | KHEDER ALRAZAA |
| No Progress | 7/16/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 7/16/2024 | KHEDER ALRAZAA |
| No Progress | 2/12/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 2/12/2025 | KHEDER ALRAZAA |
| Issued | 2/13/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 4/18/2024 | DALIA MOKAYED |
| Trees in Parkway | Cleared | 5/9/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/15/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 6/6/2024 | LUIS LUVANO |
| Permit | Cleared | 6/7/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 6/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/20/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/27/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/5/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/12/2025 | Conditional Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 10/21/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/21/2025 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 3/3/2026 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2026 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2026 | Corrections Issued | MICHEL ABAJAN |