9836 1/2 N COLUMBUS AVE 91343
Certificate Information: 9836 1/2 N COLUMBUS AVE 91343
- Application / Permit
- 24010-20000-00741
- Plan Check / Job No.
- B24VN02372
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW DETACHED 1 STORY ADU 1050 S.F. PER ORDINANCE. WORK PER ENGR.
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Current Status
- CofO Issued on 12/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2024 | MINA HABILI |
| Corrections Issued | 2/27/2024 | MINA HABILI |
| Applicant returned to address corrections | 4/24/2024 | KHUONG TRUONG |
| Plan Check Approved | 4/27/2024 | KHUONG TRUONG |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 11/5/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 12/3/2025 | RUBEN SALAS |
| Permit Finaled | 12/3/2025 | RUBEN SALAS |
| CofO Issued | 12/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 4/12/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 4/19/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/19/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 4/22/2024 | EDGAR ALCARAZ |
| ZA Case | Cleared | 4/25/2024 | NATHAN ROMINE |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/4/2024 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Reinf. Concrete | 12/5/2024 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Final | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 5/31/2025 | No Access for Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 5/31/2025 | No Access for Inspection | MISAEL ESPARZA |
| Final | 6/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/3/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/3/2025 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/3/2025 | Partial Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 8/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/5/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 8/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/5/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 8/5/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 10/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 11/4/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/4/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 11/4/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/4/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/4/2025 | Approved | JENNIFER RABUCHIN |