6605 N CANTALOUPE AVE 91405

Certificate Information: 6605 N CANTALOUPE AVE 91405

Application / Permit
24010-20000-00740
Plan Check / Job No.
B24VN02369
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/18/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2024 APPLICANT
Assigned to Plan Check Engineer 2/26/2024 JEROME MAGAT PALMA
Corrections Issued 2/27/2024 JEROME MAGAT PALMA
Building Plans Picked Up 2/29/2024 APPLICANT
Plan Check Approved 3/18/2024 GIOVANNY CHAVEZ
Issued 3/18/2024 APPLICANT
CofO in Progress 7/15/2025 RYAN SALAZAR
CofO Issued 7/16/2025 RUBEN SALAS
Permit Finaled 7/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/7/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/7/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/7/2024 CARLOS AGUILERA
Sewer availability Cleared 3/7/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2024 Partial Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/1/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 5/13/2024 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/28/2024 Approved RYAN SALAZAR
Sewer 5/28/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 9/9/2024 Approved RYAN SALAZAR
HVAC-Rough 9/9/2024 Approved RYAN SALAZAR
PLUMBING-Rough 9/9/2024 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 9/26/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 9/26/2024 Approved RYAN SALAZAR
Drywall Nailing 12/12/2024 Approved RYAN SALAZAR
Green Building Rough 12/12/2024 Approved RYAN SALAZAR
Insulation 12/12/2024 Approved RYAN SALAZAR
Shower Pan 12/12/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/30/2025 Approved JENNIFER RABUCHIN
Pre-Inspection 3/27/2025 Partial Inspection RYAN SALAZAR
BUILDING-Rough-Frame 6/13/2025 Approved RYAN SALAZAR
Final 6/13/2025 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 6/13/2025 Approved RYAN SALAZAR
Green Building Final 6/13/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 6/13/2025 Approved RYAN SALAZAR
Smoke Detectors 6/13/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 6/13/2025 Approved RYAN SALAZAR
Final 7/15/2025 OK to Issue CofO RYAN SALAZAR
Special/Order Compliance 7/15/2025 Approved RYAN SALAZAR