10249 N HILLHAVEN AVE 91042

Certificate Information: 10249 N HILLHAVEN AVE 91042

Application / Permit
24010-20000-00715
Plan Check / Job No.
B24VN01387
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) OVER 6-CAR GARAGE (NFPA-13D SPRINKLERS THROUGHOUT) (MIDDLE BUILDING)
Permit Issued
Issued on 8/13/2025
Issuing Office
Valley
Current Status
Issued on 8/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/2/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 NILOOFAR MEHRAIN
Corrections Issued 2/22/2024 PETER MOSESIAN
Quality Review Completed 2/27/2024 OMID HEDAYAT
Applicant returned to address corrections 4/21/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/1/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/24/2025 NILOOFAR MEHRAIN
Plan Check Approved 8/6/2025 NILOOFAR MEHRAIN
Issued 8/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/14/2024 CARLOS AGUILERA
Sewer availability Cleared 3/14/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/15/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/12/2024 KURT CORRAL
ZA Case Cleared 4/22/2024 MATHEW QUAN
ZA Case Cleared 4/22/2024 MATHEW QUAN
Specific Plan Cleared 4/24/2024 ERICK MARCHENA
ZI Cleared 4/24/2024 ERICK MARCHENA
Frnt yard landscape/Water mgmt Cleared 10/28/2024 MATHEW QUAN
GPI Written Notices Cleared 1/8/2025 PETER MOSESIAN
Grading Pre-Inspection Cleared 1/8/2025 PETER MOSESIAN
Roof/Waste drainage to street Cleared 7/15/2025 CARLOS AGUILERA
Low Impact Development (LID) Cleared 7/17/2025 DANIEL LEON-MENDOZA
Hold Cleared 1/23/2026 MARIA VENDIVIL

Contact Information

Contractor Atlantis Construction Services Inc; Lic. No.: 960125-B       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2026 Partial Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 2/9/2026 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval MATTHEW NELSON