NEW 64'-6" X 37' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/7/2024
Issuing Office
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 SELLA BENYAMIN
Corrections Issued 2/27/2024 SELLA BENYAMIN
Quality Review Completed 2/27/2024 STEVEN KIM
Building Plans Picked Up 3/4/2024 APPLICANT
Applicant returned to address corrections 5/16/2024 SELLA BENYAMIN
Plan Check Approved 6/7/2024 SELLA BENYAMIN
Issued 6/7/2024 APPLICANT
CofO in Progress 4/23/2025 JACK KARGODORIAN
CofO in Progress 4/23/2025 JUAN VALENZUELA
No Progress 4/24/2025 JACK KARGODORIAN
CofO Issued 9/5/2025 RUBEN SALAS
Permit Finaled 9/5/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/1/2024 CARLOS AGUILERA
Sewer availability Cleared 4/1/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/5/2024 KURT CORRAL
Trees in Parkway Cleared 4/18/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 4/25/2024 TOMMY YIN
Permit Cleared 4/25/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/29/2024 CARLOS AGUILERA
ZI Cleared 5/14/2024 JAZMIN ROQUE

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/23/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/23/2024 Approved JACK KARGODORIAN
Footing/Foundation/Slab 8/23/2024 Partial Approval JACK KARGODORIAN
Underground Mechanical 8/23/2024 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 8/28/2024 Approved JACK KARGODORIAN
Footing/Foundation/Slab 8/28/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 9/11/2024 Not Ready for Inspection JACK KARGODORIAN
Deputy Wood Construction 9/11/2024 Approved JACK KARGODORIAN
Green Building Rough 9/11/2024 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 9/11/2024 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 9/11/2024 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 9/20/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Partial Approval JACK KARGODORIAN
HVAC-Rough 10/7/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/7/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/9/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/21/2024 Corrections Issued JACK KARGODORIAN
HVAC-Rough 10/21/2024 Approved JACK KARGODORIAN
Shower Pan 10/25/2024 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/30/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 11/1/2024 Approved JACK KARGODORIAN
Insulation 11/14/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/14/2024 Partial Approval JACK KARGODORIAN
Wood Frame 11/14/2024 Approved JACK KARGODORIAN
Drywall Nailing 11/22/2024 Approved ROBERT GOLD
BUILDING-Rough-Frame 3/26/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 3/26/2025 Not Ready for Inspection JACK KARGODORIAN
Final 3/26/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 3/26/2025 Approved JACK KARGODORIAN
Green Building Rough 3/26/2025 Approved JACK KARGODORIAN
HVAC-Final 3/26/2025 Approved JACK KARGODORIAN
PLUMBING-Final 3/26/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 3/26/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 3/26/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 3/26/2025 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 4/22/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 4/22/2025 Approved JACK KARGODORIAN
Final 4/22/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 4/22/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 4/22/2025 Approved JACK KARGODORIAN
Special/Order Compliance 4/24/2025 Corrections Issued JACK KARGODORIAN