14718 W OTSEGO ST 91403
Certificate Information: 14718 W OTSEGO ST 91403
- Application / Permit
- 24010-20000-00681
- Plan Check / Job No.
- B24VN02212
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 64'-6" X 37' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | SELLA BENYAMIN |
| Corrections Issued | 2/27/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/27/2024 | STEVEN KIM |
| Building Plans Picked Up | 3/4/2024 | APPLICANT |
| Applicant returned to address corrections | 5/16/2024 | SELLA BENYAMIN |
| Plan Check Approved | 6/7/2024 | SELLA BENYAMIN |
| Issued | 6/7/2024 | APPLICANT |
| CofO in Progress | 4/23/2025 | JACK KARGODORIAN |
| CofO in Progress | 4/23/2025 | JUAN VALENZUELA |
| No Progress | 4/24/2025 | JACK KARGODORIAN |
| CofO Issued | 9/5/2025 | RUBEN SALAS |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/1/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/5/2024 | KURT CORRAL |
| Trees in Parkway | Cleared | 4/18/2024 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 4/25/2024 | TOMMY YIN |
| Permit | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/29/2024 | CARLOS AGUILERA |
| ZI | Cleared | 5/14/2024 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/23/2024 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/23/2024 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 8/23/2024 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/28/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Wood Construction | 9/11/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 9/11/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 9/11/2024 | Partial Approval | JACK KARGODORIAN |
| Deputy Wood Construction | 9/20/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 10/7/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/7/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/9/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/21/2024 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 10/21/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 10/25/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/30/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/1/2024 | Approved | JACK KARGODORIAN |
| Insulation | 11/14/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/14/2024 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 11/14/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/22/2024 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 3/26/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/26/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/26/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 3/26/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/26/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 3/26/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/26/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2025 | SGSOV Not Required | JACK KARGODORIAN |
| Service/Power Release | 3/26/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 3/26/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/26/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/22/2025 | Approved | JACK KARGODORIAN |
| Final | 4/22/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 4/22/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 4/22/2025 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 4/24/2025 | Corrections Issued | JACK KARGODORIAN |