8204 W HILLROSE ST 91040

Certificate Information: 8204 W HILLROSE ST 91040

Application / Permit
24010-20000-00666
Plan Check / Job No.
B24VN02162
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW DETACHED ACCESSORY DWELLING UNIT PER PER STATE LAW
Permit Issued
Issued on 3/12/2024
Issuing Office
Current Status
CofO Issued on 9/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/23/2024 KHUONG TRUONG
Corrections Issued 2/25/2024 KHUONG TRUONG
Applicant returned to address corrections 3/8/2024 LUKE GONZALES
Plan Check Approved 3/11/2024 LUKE GONZALES
Issued 3/12/2024 APPLICANT
CofO in Progress 9/24/2024 WILLIAM WREN
CofO Issued 9/27/2024 DANIEL ORRANTE
Permit Finaled 9/27/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/2/2024 CHARLES POWELL
Address approval Cleared 3/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/4/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/4/2024 CARLOS AGUILERA
Sewer availability Cleared 3/4/2024 CARLOS AGUILERA
Watercourse Cleared 3/4/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2024 Partial Inspection WILLIAM WREN
PLUMBING-Rough 5/21/2024 Partial Approval WILLIAM WREN
Underground Mechanical 5/21/2024 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 5/24/2024 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 5/29/2024 Approved JOHN COLEMAN
Deputy Wood Construction 6/14/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 6/26/2024 Approved WILLIAM WREN
HVAC-Rough 6/26/2024 Approved WILLIAM WREN
PLUMBING-Rough 6/26/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/28/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Approved WILLIAM WREN
Green Building Rough 6/28/2024 Approved WILLIAM WREN
Verify Sprinkler Sign Off 6/28/2024 Approved WILLIAM WREN
Insulation 7/11/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 7/11/2024 Approved WILLIAM WREN
Drywall Nailing 7/16/2024 Approved WILLIAM WREN
Shower Pan 7/30/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/5/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/26/2024 Not Ready for Inspection WILLIAM WREN
Final 8/26/2024 Corrections Issued WILLIAM WREN
Green Building Final 8/26/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Required WILLIAM WREN
Service/Power Release 8/26/2024 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 8/26/2024 Not Ready for Inspection WILLIAM WREN
Final 9/5/2024 Corrections Issued WILLIAM WREN
Green Building Final 9/5/2024 Approved WILLIAM WREN
Service/Power Release 9/5/2024 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 9/5/2024 Approved WILLIAM WREN
Final 9/12/2024 Corrections Issued WILLIAM WREN
Service/Power Release 9/12/2024 Not Required WILLIAM WREN
Final 9/23/2024 OK to Issue CofO WILLIAM WREN