14232 W EMELITA ST 91401

Certificate Information: 14232 W EMELITA ST 91401

Application / Permit
24010-20000-00649
Plan Check / Job No.
B24VN02119
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 13' X 54'-6" 1-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/24/2024
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 RAPHAEL ROSAS
Corrections Issued 2/27/2024 RAPHAEL ROSAS
Quality Review Completed 2/29/2024 STEVEN KIM
Building Plans Picked Up 3/4/2024 APPLICANT
Applicant returned to address corrections 4/29/2024 RAPHAEL ROSAS
Applicant returned to address corrections 5/13/2024 RAPHAEL ROSAS
Plan Check Approved 5/16/2024 RAPHAEL ROSAS
Issued 5/24/2024 APPLICANT
CofO in Progress 2/20/2025 RYAN SALAZAR
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/22/2024 LAVEON RIDER
Address approval Cleared 3/30/2024 CARLOS AGUILERA
Sewer availability Cleared 4/1/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/10/2024 CARLOS AGUILERA
Construction near power lines Cleared 4/30/2024 TINA MIRANDA
Low Impact Development (LID) Cleared 5/3/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/7/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/24/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 6/24/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/24/2024 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/27/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval MICHEL ABAJAN
HVAC-Rough 8/19/2024 Approved RYAN SALAZAR
PLUMBING-Rough 8/19/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 8/23/2024 Not Ready for Inspection RYAN SALAZAR
Wood Frame 8/23/2024 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 8/27/2024 Partial Inspection RYAN SALAZAR
ELECTRICAL-Rough 8/27/2024 Approved RYAN SALAZAR
Green Building Rough 8/27/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 8/27/2024 Approved RYAN SALAZAR
Insulation 8/30/2024 Approved RYAN SALAZAR
Drywall Nailing 9/4/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/4/2024 Partial Approval RYAN SALAZAR
Shower Pan 9/4/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/12/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 2/12/2025 Approved RYAN SALAZAR
Final 2/12/2025 Not Ready for Inspection RYAN SALAZAR
Footing/Foundation/Slab 2/12/2025 Approved RYAN SALAZAR
Green Building Final 2/12/2025 Approved RYAN SALAZAR
HVAC-Final 2/12/2025 Approved RYAN SALAZAR
PLUMBING-Final 2/12/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 2/12/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 2/12/2025 Approved RYAN SALAZAR
Final 2/19/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 2/19/2025 Approved RYAN SALAZAR