12003 W CANTARA ST 91605

Certificate Information: 12003 W CANTARA ST 91605

Application / Permit
24010-20000-00607
Plan Check / Job No.
B24VN02034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-6" X 33'-6" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 SELLA BENYAMIN
Corrections Issued 3/5/2024 SELLA BENYAMIN
Quality Review Completed 3/8/2024 STEVEN KIM
Building Plans Picked Up 3/20/2024 APPLICANT
Plan Check Approved 9/10/2024 SELLA BENYAMIN
Issued 9/10/2024 APPLICANT
CofO in Progress 6/4/2025 NICHOLAS TROWBRIDGE
Permit Finaled 6/10/2025 RUBEN SALAS
CofO Issued 6/10/2025 RUBEN SALAS
Permit Finaled 6/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/28/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/28/2024 CARLOS AGUILERA
Sewer availability Cleared 3/28/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 4/18/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/22/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/22/2024 LEE GUILBEAUX
Construction near power lines Cleared 8/23/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/16/2024 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/18/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Approved MATTHEW NELSON
HVAC-Rough 11/7/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 11/7/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/13/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/13/2024 Approved MICHEL ABAJAN
Green Building Rough 11/13/2024 Approved MICHEL ABAJAN
Shower Pan 11/13/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/13/2024 Approved MICHEL ABAJAN
Insulation 11/18/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/18/2024 Approved MATTHEW NELSON
Drywall Nailing 11/22/2024 Approved MICHAEL CORTEZ
Underground Mechanical 1/23/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 3/26/2025 Corrections Issued MATTHEW NELSON
Final 3/26/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 3/26/2025 Approved MATTHEW NELSON
Green Building Final 3/26/2025 Corrections Issued MATTHEW NELSON
HVAC-Final 3/26/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Final 3/26/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Not Required MATTHEW NELSON
Service/Power Release 3/26/2025 Corrections Issued MATTHEW NELSON
Smoke Detectors 3/26/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 4/10/2025 Corrections Issued MATTHEW NELSON
Final 4/10/2025 Corrections Issued MATTHEW NELSON
Green Building Final 4/10/2025 Partial Approval MATTHEW NELSON
HVAC-Final 4/10/2025 Approved MATTHEW NELSON
PLUMBING-Final 4/10/2025 Approved MATTHEW NELSON
Service/Power Release 4/10/2025 Corrections Issued MATTHEW NELSON
Final 4/22/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Final 4/22/2025 Approved NICHOLAS TROWBRIDGE
Service/Power Release 4/22/2025 Approved NICHOLAS TROWBRIDGE
Special/Order Compliance 5/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Final 6/3/2025 OK to Issue CofO NICHOLAS TROWBRIDGE