7746 N SHADYSPRING PL 91504
Certificate Information: 7746 N SHADYSPRING PL 91504
- Application / Permit
- 24010-20000-00600
- Plan Check / Job No.
- B24VN01987
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New irregular shaped 31' 7" x 36' one story ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineer.
- Permit Issued
- Issued on 9/27/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | NAREG ATARIAN |
| Corrections Issued | 3/7/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/11/2024 | OMID HEDAYAT |
| Plan Check Approved | 7/5/2024 | NAREG ATARIAN |
| Issued | 9/27/2024 | APPLICANT |
| CofO in Progress | 5/22/2025 | DAVID ANDERSON |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| CofO Issued | 6/3/2025 | RUBEN SALAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/28/2024 | CHARLES POWELL |
| Address approval | Cleared | 3/30/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/1/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/23/2024 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 6/18/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/20/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 7/3/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/3/2024 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 7/5/2024 | RUSSELL BONVOULOIR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/2/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 10/2/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Posting Pre-Inspection | 10/2/2024 | Approved | DAVID ANDERSON |
| Pre-Inspection | 10/2/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/4/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 10/8/2024 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 10/31/2024 | Approved | DAVID ANDERSON |
| Sewer | 10/31/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/8/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 11/8/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 12/2/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/2/2024 | Approved | DAVID ANDERSON |
| Wood Frame | 12/2/2024 | Approved | DAVID ANDERSON |
| Insulation | 12/12/2024 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/12/2024 | Approved | AMY COLIN |
| Drywall Nailing | 12/23/2024 | Approved | WILLIAM WREN |
| Shower Pan | 1/7/2025 | Approved | DAVID ANDERSON |
| Underground Mechanical | 1/24/2025 | Partial Approval | DAVID ANDERSON |
| Final | 4/15/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/15/2025 | Approved | DAVID ANDERSON |
| MERV13>=Final | 4/15/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 4/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 4/15/2025 | Approved | DAVID ANDERSON |
| Final | 5/14/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 5/14/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 5/19/2025 | Corrections Issued | DAVID MATSON |
| Service/Power Release | 5/19/2025 | Not Ready for Inspection | DAVID MATSON |
| Final | 5/21/2025 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 5/21/2025 | Approved | DAVID ANDERSON |