7746 N SHADYSPRING PL 91504

Certificate Information: 7746 N SHADYSPRING PL 91504

Application / Permit
24010-20000-00600
Plan Check / Job No.
B24VN01987
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New irregular shaped 31' 7" x 36' one story ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineer.
Permit Issued
Issued on 9/27/2024
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 NAREG ATARIAN
Corrections Issued 3/7/2024 NAREG ATARIAN
Quality Review Completed 3/11/2024 OMID HEDAYAT
Plan Check Approved 7/5/2024 NAREG ATARIAN
Issued 9/27/2024 APPLICANT
CofO in Progress 5/22/2025 DAVID ANDERSON
Permit Finaled 6/3/2025 RUBEN SALAS
CofO Issued 6/3/2025 RUBEN SALAS
Permit Finaled 6/3/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/28/2024 CHARLES POWELL
Address approval Cleared 3/30/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/1/2024 CARLOS AGUILERA
Sewer availability Cleared 4/1/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/23/2024 MATTHEW CRAIG
Low Impact Development (LID) Cleared 6/18/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 6/20/2024 EDGAR ALCARAZ
Construction near power lines Cleared 7/3/2024 RIDWAN HARDY
Construction within easement Cleared 7/3/2024 RIDWAN HARDY
GPI Written Notices Cleared 7/5/2024 RUSSELL BONVOULOIR

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/2/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 10/2/2024 Not Ready for Inspection DAVID ANDERSON
Posting Pre-Inspection 10/2/2024 Approved DAVID ANDERSON
Pre-Inspection 10/2/2024 Approved DAVID ANDERSON
PLUMBING-Rough 10/4/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 10/8/2024 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 10/11/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval DAVID ANDERSON
PLUMBING-Rough 10/31/2024 Approved DAVID ANDERSON
Sewer 10/31/2024 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/8/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Approved JACK KARGODORIAN
HVAC-Rough 11/8/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/2/2024 Approved DAVID ANDERSON
MERV13>=Rough 12/2/2024 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 12/2/2024 Approved DAVID ANDERSON
Wood Frame 12/2/2024 Approved DAVID ANDERSON
Insulation 12/12/2024 Approved AMY COLIN
Interior/Exterior Lathing 12/12/2024 Approved AMY COLIN
Drywall Nailing 12/23/2024 Approved WILLIAM WREN
Shower Pan 1/7/2025 Approved DAVID ANDERSON
Underground Mechanical 1/24/2025 Partial Approval DAVID ANDERSON
Final 4/15/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 4/15/2025 Approved DAVID ANDERSON
MERV13>=Final 4/15/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/15/2025 SGSOV Not Required DAVID ANDERSON
Service/Power Release 4/15/2025 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 4/15/2025 Approved DAVID ANDERSON
Final 5/14/2025 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 5/14/2025 Not Ready for Inspection DAVID ANDERSON
Final 5/19/2025 Corrections Issued DAVID MATSON
Service/Power Release 5/19/2025 Not Ready for Inspection DAVID MATSON
Final 5/21/2025 OK to Issue CofO DAVID ANDERSON
Service/Power Release 5/21/2025 Approved DAVID ANDERSON