276 1/2-2/3 E 47TH ST 90011
Certificate Information: 276 1/2-2/3 E 47TH ST 90011
- Application / Permit
- 24010-20000-00598
- Plan Check / Job No.
- B24VN01971
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached two story 28' x 32' (2 ADU's) per GC 66323(a)(4) . All work done per engineer.
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | NAREG ATARIAN |
| Corrections Issued | 3/6/2024 | NAREG ATARIAN |
| Quality Review Completed | 3/7/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/9/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 2/25/2025 | NAREG ATARIAN |
| Plan Check Approved | 3/7/2025 | NAREG ATARIAN |
| Issued | 4/3/2025 | APPLICANT |
| CofO in Progress | 2/26/2026 | SABAS ALONSO |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
| CofO Issued | 2/27/2026 | DEROLD HAUFF |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | KEVIN AVILA |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 4/25/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 5/17/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 9/16/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/16/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Nwabuzor Construction; Lic. No.: 1073216-B | , |
| Contractor | R N Investments And Community Services Inc; Lic. No.: 1073216-B | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 7/29/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/20/2025 | Conditional Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 9/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 9/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/1/2025 | Corrections Issued | ENRIQUE MIRELES |
| Insulation | 10/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 10/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/15/2025 | Approved | ANTHONY RAMOS |
| Insulation | 10/15/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/15/2025 | Approved | ANTHONY RAMOS |
| Final | 1/5/2026 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 1/5/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/9/2026 | Corrections Issued | SABAS ALONSO |
| Smoke Detectors | 1/9/2026 | Approved | SABAS ALONSO |
| Final | 1/28/2026 | Corrections Issued | SABAS ALONSO |
| Deputy Steel/Welding | 2/11/2026 | Conditional Approval | ALEX COLIN |
| Final | 2/23/2026 | OK to Issue CofO | SABAS ALONSO |