7650 N INDEPENDENCE AVE 91304

Certificate Information: 7650 N INDEPENDENCE AVE 91304

Application / Permit
24010-20000-00569
Plan Check / Job No.
B24VN01907
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 9/3/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/14/2024 JEROME MAGAT PALMA
Corrections Issued 2/14/2024 JEROME MAGAT PALMA
Building Plans Picked Up 2/27/2024 APPLICANT
Applicant returned to address corrections 8/27/2024 MADISON ODELL
Plan Check Approved 9/3/2024 ROSENDO MEDINA
Issued 9/3/2024 APPLICANT
CofO in Progress 7/9/2025 ALEXANDER HANDY
Permit Finaled 8/19/2025 JOHN JANSON
CofO Issued 8/19/2025 JOHN JANSON
Permit Finaled 8/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/5/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/7/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/7/2024 CARLOS RAMIREZ
Construction near power lines Cleared 7/7/2024 RIDWAN HARDY
Construction within easement Cleared 7/7/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 8/26/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 8/27/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/17/2024 Partial Approval ALEXANDER HANDY
Sewer 9/26/2024 Approved ALEXANDER HANDY
Footing/Foundation/Slab 10/11/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 12/30/2024 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 12/30/2024 Corrections Issued ALEXANDER HANDY
HVAC-Rough 12/30/2024 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 12/30/2024 Approved ALEXANDER HANDY
Insulation 1/15/2025 Corrections Issued ALEXANDER HANDY
Interior/Exterior Lathing 1/15/2025 Partial Approval ALEXANDER HANDY
Shower Pan 1/15/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 1/29/2025 Not Ready for Inspection SCOTT SOBEL
Drywall Nailing 1/29/2025 Corrections Issued SCOTT SOBEL
Green Building Rough 1/29/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 1/29/2025 Partial Approval SCOTT SOBEL
Drywall Nailing 2/3/2025 Approved SCOTT SOBEL
Insulation 2/3/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 2/3/2025 Approved SCOTT SOBEL
Shower Pan 2/3/2025 Approved SCOTT SOBEL
BUILDING-Rough-Frame 7/1/2025 Approved HENRY KIM
ELECTRICAL-Final 7/1/2025 Corrections Issued HENRY KIM
Final 7/1/2025 Not Ready for Inspection HENRY KIM
Green Building Final 7/1/2025 Approved HENRY KIM
HVAC-Final 7/1/2025 Approved HENRY KIM
PLUMBING-Final 7/1/2025 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Gas Company HENRY KIM
Service/Power Release 7/1/2025 Not Ready for Inspection HENRY KIM
Smoke Detectors 7/1/2025 Approved HENRY KIM
Verify Sprinkler Sign Off 7/1/2025 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 7/8/2025 Approved ALEXANDER HANDY
Final 7/8/2025 OK to Issue CofO ALEXANDER HANDY
PLUMBING-Final 7/8/2025 Approved ALEXANDER HANDY
Service/Power Release 7/8/2025 Approved ALEXANDER HANDY