4431 E SINOVA ST 90032

Certificate Information: 4431 E SINOVA ST 90032

Application / Permit
24010-20000-00546
Plan Check / Job No.
B23LA24811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 30' x 20' 3" ADU per LAMC 12.22 A.33 (c) - (d), NFPA 13D sprinkler required. All work done per engineer. Comply with Department Order effective date 07/25/2024. Permit will expire 30 days from Issuance date
Permit Issued
Issued on 9/22/2024
Issuing Office
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 NAREG ATARIAN
Corrections Issued 2/11/2024 NAREG ATARIAN
Quality Review Completed 2/12/2024 OMID HEDAYAT
Applicant returned to address corrections 5/30/2024 NAREG ATARIAN
Applicant returned to address corrections 8/9/2024 NAREG ATARIAN
Applicant returned to address corrections 8/21/2024 NAREG ATARIAN
Applicant returned to address corrections 8/29/2024 NAREG ATARIAN
Applicant returned to address corrections 9/10/2024 NAREG ATARIAN
Applicant returned to address corrections 9/19/2024 NAREG ATARIAN
Plan Check Approved 9/20/2024 NAREG ATARIAN
Issued 9/22/2024 APPLICANT
CofO in Progress 2/19/2026 DANIEL DELACRUZ
Permit Finaled 3/12/2026 DANIEL SANCHEZ
CofO Issued 3/12/2026 DANIEL SANCHEZ
Permit Finaled 3/12/2026 DANIEL SANCHEZ

Permit Application Clearance Information

ZA Case Cleared 4/15/2024 YINGSHI HUANG
Address approval Cleared 5/3/2024 TREVOR QUAN
BHO/Hillside ordinance Cleared 5/3/2024 TREVOR QUAN
Hydrant and Access approval Cleared 5/24/2024 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 7/10/2024 TREVOR QUAN
Sewer availability Cleared 7/10/2024 TREVOR QUAN
"D" conditions Cleared 7/31/2024 JAZMIN ROQUE
"Q" conditions Cleared 7/31/2024 JAZMIN ROQUE
ZI Cleared 7/31/2024 JAZMIN ROQUE
Low Impact Development (LID) Cleared 8/5/2024 MITESH PATEL
GPI Written Notices Cleared 8/21/2024 SERGIO VALENZUELA
Grading Pre-Inspection Cleared 8/21/2024 LANNY MERRICK
Roof/Waste drainage to street Cleared 8/21/2024 CELINA MORENO
Miscellaneous Cleared 8/26/2024 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205
Engineer Adzhemyan,, Arsen; Lic. No.: NA89103       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Stumpf,, Patricio L; Lic. No.: L5515 10527 SAN VINCENTE AVE      SOUTH GATE, CA 90280

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2024 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Rough 10/9/2024 Partial Approval PEDRO SIERRA
Excavation/Setback/Form/Re-Bar 10/11/2024 Corrections Issued PEDRO SIERRA
Footing/Foundation/Slab 10/11/2024 Approved PEDRO SIERRA
Special/Order Compliance 10/21/2024 Corrections Issued DANIEL DELACRUZ
Order to Comply 10/25/2024 Not Required PEDRO SIERRA
Excavation/Setback/Form/Re-Bar 10/28/2024 Approved DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Approved DANIEL DELACRUZ
ELECTRICAL-Rough 1/3/2025 Approved PEDRO SIERRA
Sewer 1/3/2025 Approved PEDRO SIERRA
ELECTRICAL-Rough 1/13/2025 Approved DANIEL DELACRUZ
HVAC-Rough 1/13/2025 Approved DANIEL DELACRUZ
Shower Pan 1/13/2025 Approved DANIEL DELACRUZ
BUILDING-Rough-Frame 1/21/2025 Partial Approval DANIEL DELACRUZ
PLUMBING-Rough 1/21/2025 Approved DANIEL DELACRUZ
BUILDING-Rough-Frame 1/28/2025 Approved PEDRO SIERRA
Green Building Rough 1/28/2025 Approved PEDRO SIERRA
Insulation 1/28/2025 Approved PEDRO SIERRA
Interior/Exterior Lathing 1/28/2025 Approved PEDRO SIERRA
Verify Sprinkler Sign Off 1/28/2025 Approved PEDRO SIERRA
Drywall Nailing 2/6/2025 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 2/6/2025 Approved DANIEL DELACRUZ
HVAC-Rough 4/24/2025 Approved DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Ready PEDRO SIERRA
ELECTRICAL-Final 5/22/2025 Not Ready for Inspection PEDRO SIERRA
ELECTRICAL-Final 5/27/2025 Approved DANIEL DELACRUZ
Green Building Final 5/27/2025 Approved DANIEL DELACRUZ
HVAC-Final 5/27/2025 Approved DANIEL DELACRUZ
PLUMBING-Final 5/27/2025 Approved DANIEL DELACRUZ
Final 6/3/2025 Not Ready for Inspection DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Required DANIEL DELACRUZ
Service/Power Release 6/3/2025 Approved DANIEL DELACRUZ
Smoke Detectors 6/3/2025 Partial Approval DANIEL DELACRUZ
Final 7/23/2025 Not Ready for Inspection DANIEL DELACRUZ
Smoke Detectors 7/23/2025 Not Ready for Inspection DANIEL DELACRUZ
Final 2/18/2026 OK to Issue CofO DANIEL DELACRUZ
Smoke Detectors 2/18/2026 Approved DANIEL DELACRUZ