4431 E SINOVA ST 90032
Certificate Information: 4431 E SINOVA ST 90032
- Application / Permit
- 24010-20000-00546
- Plan Check / Job No.
- B23LA24811
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 30' x 20' 3" ADU per LAMC 12.22 A.33 (c) - (d), NFPA 13D sprinkler required. All work done per engineer. Comply with Department Order effective date 07/25/2024. Permit will expire 30 days from Issuance date
- Permit Issued
- Issued on 9/22/2024
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | NAREG ATARIAN |
| Corrections Issued | 2/11/2024 | NAREG ATARIAN |
| Quality Review Completed | 2/12/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/30/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/9/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/21/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 8/29/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/10/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/19/2024 | NAREG ATARIAN |
| Plan Check Approved | 9/20/2024 | NAREG ATARIAN |
| Issued | 9/22/2024 | APPLICANT |
| CofO in Progress | 2/19/2026 | DANIEL DELACRUZ |
| Permit Finaled | 3/12/2026 | DANIEL SANCHEZ |
| CofO Issued | 3/12/2026 | DANIEL SANCHEZ |
| Permit Finaled | 3/12/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| ZA Case | Cleared | 4/15/2024 | YINGSHI HUANG |
| Address approval | Cleared | 5/3/2024 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 5/3/2024 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 5/24/2024 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 7/10/2024 | TREVOR QUAN |
| "D" conditions | Cleared | 7/31/2024 | JAZMIN ROQUE |
| "Q" conditions | Cleared | 7/31/2024 | JAZMIN ROQUE |
| ZI | Cleared | 7/31/2024 | JAZMIN ROQUE |
| Low Impact Development (LID) | Cleared | 8/5/2024 | MITESH PATEL |
| GPI Written Notices | Cleared | 8/21/2024 | SERGIO VALENZUELA |
| Grading Pre-Inspection | Cleared | 8/21/2024 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | CELINA MORENO |
| Miscellaneous | Cleared | 8/26/2024 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: NA89103 | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
| Engineer | Stumpf,, Patricio L; Lic. No.: L5515 | 10527 SAN VINCENTE AVE SOUTH GATE, CA 90280 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| PLUMBING-Rough | 10/9/2024 | Partial Approval | PEDRO SIERRA |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Corrections Issued | PEDRO SIERRA |
| Footing/Foundation/Slab | 10/11/2024 | Approved | PEDRO SIERRA |
| Special/Order Compliance | 10/21/2024 | Corrections Issued | DANIEL DELACRUZ |
| Order to Comply | 10/25/2024 | Not Required | PEDRO SIERRA |
| Excavation/Setback/Form/Re-Bar | 10/28/2024 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 1/3/2025 | Approved | PEDRO SIERRA |
| Sewer | 1/3/2025 | Approved | PEDRO SIERRA |
| ELECTRICAL-Rough | 1/13/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 1/13/2025 | Approved | DANIEL DELACRUZ |
| Shower Pan | 1/13/2025 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 1/21/2025 | Partial Approval | DANIEL DELACRUZ |
| PLUMBING-Rough | 1/21/2025 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | PEDRO SIERRA |
| Green Building Rough | 1/28/2025 | Approved | PEDRO SIERRA |
| Insulation | 1/28/2025 | Approved | PEDRO SIERRA |
| Interior/Exterior Lathing | 1/28/2025 | Approved | PEDRO SIERRA |
| Verify Sprinkler Sign Off | 1/28/2025 | Approved | PEDRO SIERRA |
| Drywall Nailing | 2/6/2025 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 2/6/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 4/24/2025 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Not Ready | PEDRO SIERRA |
| ELECTRICAL-Final | 5/22/2025 | Not Ready for Inspection | PEDRO SIERRA |
| ELECTRICAL-Final | 5/27/2025 | Approved | DANIEL DELACRUZ |
| Green Building Final | 5/27/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 5/27/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 5/27/2025 | Approved | DANIEL DELACRUZ |
| Final | 6/3/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Required | DANIEL DELACRUZ |
| Service/Power Release | 6/3/2025 | Approved | DANIEL DELACRUZ |
| Smoke Detectors | 6/3/2025 | Partial Approval | DANIEL DELACRUZ |
| Final | 7/23/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Smoke Detectors | 7/23/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Final | 2/18/2026 | OK to Issue CofO | DANIEL DELACRUZ |
| Smoke Detectors | 2/18/2026 | Approved | DANIEL DELACRUZ |