16711 W MOORPARK ST 91436

Certificate Information: 16711 W MOORPARK ST 91436

Application / Permit
24010-20000-00522
Plan Check / Job No.
B24VN01801
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 111'5" X 45' TWO STORY SFD WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/23/2024
Issuing Office
Current Status
CofO Issued on 10/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 RARES BODEA
Corrections Issued 2/20/2024 RARES BODEA
Quality Review Completed 2/23/2024 STEVEN KIM
Building Plans Picked Up 2/28/2024 APPLICANT
Plan Check Approved 5/23/2024 RARES BODEA
Issued 5/23/2024 APPLICANT
CofO in Progress 8/4/2025 THOMAS FINNILA
CofO in Progress 10/1/2025 THOMAS FINNILA
No Progress 10/2/2025 SEAN WIRCH
CofO in Progress 10/2/2025 SEAN WIRCH
Permit Finaled 10/20/2025 JOHN JANSON
CofO Issued 10/20/2025 JOHN JANSON
Permit Finaled 10/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 3/14/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/15/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 4/1/2024 KURT CORRAL
Low Impact Development (LID) Cleared 4/10/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/11/2024 EDGAR ALCARAZ
Trees in Parkway Cleared 4/15/2024 ADALBERTO VERA
Permit Cleared 4/16/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/10/2024 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/21/2024 No Access for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/21/2024 No Access for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/25/2024 Approved THOMAS FINNILA
Footing/Foundation/Slab 6/25/2024 Approved THOMAS FINNILA
Deputy Reinf. Concrete 6/26/2024 Conditional Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval ALEXANDER HANDY
HVAC-Rough 9/3/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 9/9/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 9/9/2024 Approved THOMAS FINNILA
HVAC-Rough 9/11/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 9/12/2024 Approved SEAN WIRCH
BUILDING-Rough-Frame 10/7/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 10/8/2024 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/15/2024 Partial Approval THOMAS FINNILA
HVAC-Rough 10/15/2024 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 10/28/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/31/2024 Approved THOMAS FINNILA
Green Building Rough 10/31/2024 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 10/31/2024 Approved THOMAS FINNILA
Insulation 11/6/2024 Approved SCOTT SOBEL
Shower Pan 11/8/2024 Approved SCOTT SOBEL
Drywall Nailing 11/14/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/14/2024 Approved MORRIS JACKSON
Underground Mechanical 1/10/2025 Partial Approval THOMAS FINNILA
HVAC-Final 6/16/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 6/16/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 6/23/2025 Conditional Approval THOMAS FINNILA
PLUMBING-Final 6/23/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 6/27/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 7/2/2025 Approved SEAN WIRCH
Final 7/2/2025 Not Ready for Inspection SEAN WIRCH
Service/Power Release 7/2/2025 Approved SEAN WIRCH
ELECTRICAL-Final 7/11/2025 Approved THOMAS FINNILA
Final 7/11/2025 OK to Issue CofO THOMAS FINNILA
Green Building Final 7/11/2025 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Required THOMAS FINNILA
Smoke Detectors 7/11/2025 Approved THOMAS FINNILA
Final 8/4/2025 OK to Issue CofO THOMAS FINNILA
Deputy Drilled-In Anchors 10/2/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 10/2/2025 Partial Approval SEAN WIRCH
Special/Order Compliance 10/6/2025 Corrections Issued THOMAS FINNILA