16711 W MOORPARK ST 91436
Certificate Information: 16711 W MOORPARK ST 91436
- Application / Permit
- 24010-20000-00522
- Plan Check / Job No.
- B24VN01801
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 111'5" X 45' TWO STORY SFD WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/23/2024
- Issuing Office
- Current Status
- CofO Issued on 10/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | RARES BODEA |
| Corrections Issued | 2/20/2024 | RARES BODEA |
| Quality Review Completed | 2/23/2024 | STEVEN KIM |
| Building Plans Picked Up | 2/28/2024 | APPLICANT |
| Plan Check Approved | 5/23/2024 | RARES BODEA |
| Issued | 5/23/2024 | APPLICANT |
| CofO in Progress | 8/4/2025 | THOMAS FINNILA |
| CofO in Progress | 10/1/2025 | THOMAS FINNILA |
| No Progress | 10/2/2025 | SEAN WIRCH |
| CofO in Progress | 10/2/2025 | SEAN WIRCH |
| Permit Finaled | 10/20/2025 | JOHN JANSON |
| CofO Issued | 10/20/2025 | JOHN JANSON |
| Permit Finaled | 10/20/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/15/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 4/1/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 4/10/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/11/2024 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 4/15/2024 | ADALBERTO VERA |
| Permit | Cleared | 4/16/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/10/2024 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/21/2024 | No Access for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/21/2024 | No Access for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/25/2024 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/26/2024 | Conditional Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | ALEXANDER HANDY |
| HVAC-Rough | 9/3/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/9/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/9/2024 | Approved | THOMAS FINNILA |
| HVAC-Rough | 9/11/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/12/2024 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 10/7/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 10/8/2024 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/15/2024 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 10/15/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/28/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/31/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/31/2024 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/31/2024 | Approved | THOMAS FINNILA |
| Insulation | 11/6/2024 | Approved | SCOTT SOBEL |
| Shower Pan | 11/8/2024 | Approved | SCOTT SOBEL |
| Drywall Nailing | 11/14/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/14/2024 | Approved | MORRIS JACKSON |
| Underground Mechanical | 1/10/2025 | Partial Approval | THOMAS FINNILA |
| HVAC-Final | 6/16/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 6/16/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 6/23/2025 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 6/23/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/27/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/2/2025 | Approved | SEAN WIRCH |
| Final | 7/2/2025 | Not Ready for Inspection | SEAN WIRCH |
| Service/Power Release | 7/2/2025 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 7/11/2025 | Approved | THOMAS FINNILA |
| Final | 7/11/2025 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 7/11/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Not Required | THOMAS FINNILA |
| Smoke Detectors | 7/11/2025 | Approved | THOMAS FINNILA |
| Final | 8/4/2025 | OK to Issue CofO | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 10/2/2025 | Partial Approval | SEAN WIRCH |
| Deputy Reinf. Concrete | 10/2/2025 | Partial Approval | SEAN WIRCH |
| Special/Order Compliance | 10/6/2025 | Corrections Issued | THOMAS FINNILA |