12025 W WILLARD ST 91605

Certificate Information: 12025 W WILLARD ST 91605

Application / Permit
24010-20000-00512
Plan Check / Job No.
B24VN01766
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 44'-0" X 22'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. (SEE COMMENTS)
Permit Issued
Issued on 8/2/2024
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2024 APPLICANT
Assigned to Plan Check Engineer 2/14/2024 ARTIN ZARUKIAN
Corrections Issued 2/17/2024 ARTIN ZARUKIAN
Building Plans Picked Up 2/22/2024 APPLICANT
Applicant returned to address corrections 4/30/2024 ALEC MOUSAKHANIAN
Plan Check Approved 8/2/2024 GIOVANNY CHAVEZ
Issued 8/2/2024 APPLICANT
CofO in Progress 1/31/2025 MATTHEW NELSON
Permit Finaled 2/6/2025 RUBEN SALAS
CofO Issued 2/6/2025 RUBEN SALAS
Permit Finaled 2/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/20/2024 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 2/24/2024 COLIN LOREDO
Sewer availability Cleared 2/24/2024 COLIN LOREDO
Construction near power lines Cleared 7/15/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 7/17/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 7/18/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2024 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 8/22/2024 Approved MATTHEW NELSON
Deputy Reinf. Concrete 8/23/2024 Conditional Approval MATTHEW NELSON
Wood Frame 9/9/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 9/12/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 9/12/2024 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 9/12/2024 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 9/25/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 9/25/2024 Approved MATTHEW NELSON
Green Building Rough 9/25/2024 Approved MATTHEW NELSON
HVAC-Rough 9/25/2024 Approved MATTHEW NELSON
PLUMBING-Rough 9/25/2024 Approved MATTHEW NELSON
PLUMBING-Rough 9/27/2024 Partial Approval MATTHEW NELSON
Insulation 10/3/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/3/2024 Partial Approval MATTHEW NELSON
Drywall Nailing 10/8/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/9/2024 Approved DAVID ANDERSON
Final 12/9/2024 Corrections Issued DAVID ANDERSON
Green Building Final 12/9/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Not Required DAVID ANDERSON
Service/Power Release 12/9/2024 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 12/9/2024 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 12/9/2024 Approved DAVID ANDERSON
Final 12/23/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Final 12/23/2024 Not Ready for Inspection MATTHEW NELSON
Service/Power Release 12/23/2024 Corrections Issued MATTHEW NELSON
Final 1/29/2025 OK to Issue CofO MATTHEW NELSON
Green Building Final 1/29/2025 Approved MATTHEW NELSON
Service/Power Release 1/29/2025 Approved MATTHEW NELSON