1234 W 59TH PL 90044

Certificate Information: 1234 W 59TH PL 90044

Application / Permit
24010-20000-00492
Plan Check / Job No.
B24VN01715
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER LAMC 12.22 A.33 (c)-(d) (2-STORY)
Permit Issued
Issued on 9/11/2024
Issuing Office
Current Status
Issued on 9/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/27/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 CARLOS MONTES
Corrections Issued 4/1/2024 CARLOS MONTES
Quality Review Completed 4/2/2024 GARO TELMI
Applicant returned to address corrections 6/20/2024 CARLOS MONTES
Plan Check Approved 9/11/2024 CARLOS MONTES
Issued 9/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/16/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/17/2024 WALLIE JONG
Sewer availability Cleared 7/17/2024 WALLIE JONG
Low Impact Development (LID) Cleared 8/23/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/27/2024 WALLIE JONG

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/26/2024 Conditional Approval JOHN QUINTANILLA
Underground Mechanical 9/26/2024 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 10/3/2024 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Approved CRAIG DAVIS
ELECTRICAL-Rough 10/28/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 10/28/2024 Approved CRAIG DAVIS
PLUMBING-Rough 10/28/2024 Corrections Issued CRAIG DAVIS
Shower Pan 10/28/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 10/30/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/30/2024 Not Ready for Inspection SABAS ALONSO
Green Building Rough 10/30/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 10/30/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 10/30/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 10/30/2024 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 10/30/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/1/2024 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 11/1/2024 Partial Approval CRAIG DAVIS
Wood Frame 11/1/2024 Partial Approval CRAIG DAVIS
Insulation 11/7/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 11/12/2024 Partial Approval CRAIG DAVIS
Drywall Nailing 11/12/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 11/12/2024 Approved CRAIG DAVIS
Green Building Rough 11/12/2024 Approved CRAIG DAVIS
Drywall Nailing 11/13/2024 Approved CRAIG DAVIS
Final 2/4/2025 Corrections Issued BARRY HACHE
Green Building Final 2/4/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Not Required BARRY HACHE
Service/Power Release 2/4/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 2/4/2025 Approved BARRY HACHE
Verify Sprinkler Sign Off 2/4/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 2/25/2025 Approved BARRY HACHE
Final 2/25/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 2/25/2025 Approved BARRY HACHE
Green Building Final 2/25/2025 Approved BARRY HACHE
Service/Power Release 2/25/2025 Not Ready for Inspection BARRY HACHE