1553-1555 E 55TH ST 90011

Certificate Information: 1553-1555 E 55TH ST 90011

Application / Permit
24010-20000-00467
Plan Check / Job No.
B24VN01593
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(ePLAN) New 2-story duplex with attached garages. All work per engineer.
Permit Issued
Issued on 7/23/2024
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 VICTOR CHEN
Corrections Issued 2/13/2024 VICTOR CHEN
Quality Review Completed 2/28/2024 HAMID REZAEI
Applicant returned to address corrections 6/11/2024 VICTOR CHEN
Applicant returned to address corrections 7/11/2024 VICTOR CHEN
Plan Check Approved 7/15/2024 VICTOR CHEN
Issued 7/23/2024 APPLICANT
CofO in Progress 12/31/2024 SABAS ALONSO
Permit Finaled 1/2/2025 DEROLD HAUFF
CofO Issued 1/2/2025 DEROLD HAUFF
Permit Finaled 1/2/2025 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 3/8/2024 RUBEN VASQUEZ
ZA Case Cleared 3/8/2024 RUBEN VASQUEZ
Address approval Cleared 3/15/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/20/2024 JEANIE LAM
Low Impact Development (LID) Cleared 3/20/2024 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/21/2024 JEANIE LAM
Hydrant and Access approval Cleared 3/22/2024 LAVEON RIDER
SB8 RUD Cleared 4/15/2024 PETER MONTI
Sewer availability Cleared 5/15/2024 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/23/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/5/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 9/5/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 9/6/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 10/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/22/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/23/2024 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/23/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/24/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/28/2024 Approved ALEJANDRO DE ARTOLA
Insulation 10/28/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 11/8/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 11/8/2024 Approved JOSH MEISTER
ELECTRICAL-Final 12/13/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 12/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/27/2024 Approved SABAS ALONSO
Final 12/27/2024 Conditional Approval SABAS ALONSO
HVAC-Final 12/27/2024 Approved SABAS ALONSO
PLUMBING-Final 12/27/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Not Required SABAS ALONSO
Service/Power Release 12/27/2024 Approved SABAS ALONSO
Smoke Detectors 12/27/2024 Approved SABAS ALONSO
Final 12/30/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 12/30/2024 Approved SABAS ALONSO