6661 N ETHEL AVE 91606
Certificate Information: 6661 N ETHEL AVE 91606
- Application / Permit
- 24010-20000-00451
- Plan Check / Job No.
- B24VN01524
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 8/14/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 2/9/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/14/2024 | APPLICANT |
| Applicant returned to address corrections | 7/22/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/7/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 8/14/2024 | ROSENDO MEDINA |
| Issued | 8/14/2024 | APPLICANT |
| CofO in Progress | 8/13/2025 | OGANES TARAKHCHYAN |
| CofO in Progress | 8/13/2025 | JOAQUIN GREENOUGH |
| Permit Finaled | 8/18/2025 | RUBEN SALAS |
| CofO Issued | 8/18/2025 | RUBEN SALAS |
| Permit Finaled | 8/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/21/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 6/21/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 7/17/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Trig Builders Inc; Lic. No.: 1030887-B | 6442 COLDWATER CANYON AVE 111 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Approved | GAREN HAYRAPETYAN |
| Sewer | 12/2/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/10/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/10/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/12/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/12/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/20/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/20/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/24/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/24/2024 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 12/26/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 12/26/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 12/26/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 1/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 1/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 1/29/2025 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 1/29/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 2/5/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/10/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/28/2025 | Approved | JACK KARGODORIAN |
| Final | 4/28/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/28/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 4/28/2025 | Approved | JACK KARGODORIAN |
| Service/Power Release | 4/28/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 4/28/2025 | Approved | JACK KARGODORIAN |
| Final | 7/28/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 7/28/2025 | Approved | OGANES TARAKHCHYAN |